Overlay dam unit price, Indiana

Low bidders on INDOT contracts carried a median of $76.00 per SFT for item 722-51874, overlay dam, over the 24 months to 05 NOV 2026, across 60 low bids. Half of all 254 bids fell between $52.00 and $98.75.

Owner
Indiana DOT
Item
722-51874
Unit
SFT
Latest letting
05 NOV 2026
$76.00Low bidder's median, per SFT
$78.78Median of all bids, per SFT
60Contracts in the window

By year of letting

Overlay dam, INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222322$72.7568$70.00
20232525$90.0084$85.50
20243232$75.00132$75.00
20253131$75.00127$75.19
20262222$68.5096$78.21
Overlay dam, INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Overlay dam, INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Seymour17$75.0081$75.00
Vincennes12$61.0050$65.00
LaPorte12$85.0048$78.88
Fort Wayne9$65.0035$80.00
Crawfordsville6$89.0526$93.70
Greenfield4$86.5714$89.50
Overlay dam, INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Overlay dam, INDOT: low bidder's median by quantity band
Quantity (SFT)Low bidsLow-bid median
24 to 8815$84.50
88 to 124.5015$68.14
125 to 19115$75.00
197 to 84015$60.00
Overlay dam, INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Overlay dam
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
05 NOV 2026B-44466-ASeymour142$80.00$65.007E & B PAVING LLCINDOT
05 NOV 2026B-44534-AFort Wayne840$65.00$82.924E & B PAVING LLCINDOT
07 OCT 2026B-43353-ALaPorte292$40.00$85.006PIONEER ASSOCIATES, INC.INDOT
07 OCT 2026B-44530-AFort Wayne92$49.25$52.124MILESTONE CONTRACTORS LPINDOT
07 OCT 2026B-44532-AFort Wayne197$67.00$78.504MILESTONE CONTRACTORS LPINDOT
07 OCT 2026B-44578-AGreenfield104$105.00$89.504E & B PAVING LLCINDOT
02 SEP 2026B-44473-ASeymour180$77.00$75.005FORCE CONSTRUCTION CO INCINDOT
02 SEP 2026B-45066-AFort Wayne92$55.00$85.005PIONEER ASSOCIATES, INC.INDOT
05 AUG 2026B-44405-ASeymour254$60.00$92.753BEATY CONSTRUCTION, INC.INDOT
05 AUG 2026B-44406-ASeymour125$20.00$55.007CLR, INC.INDOT
05 AUG 2026B-44407-ASeymour102$110.00$101.004MILESTONE CONTRACTORS LPINDOT
08 JUL 2026B-46217-ASeymour90$20.00$84.508DAVE O'MARA CONTRACTOR INCINDOT
07 MAY 2026B-43355-ALaPorte88$70.00$70.004RIETH-RILEY CONSTRUCTION CO., INC.INDOT
08 APR 2026R-42521-ACrawfordsville79$93.10$96.054RIETH-RILEY CONSTRUCTION CO., INC.INDOT
11 MAR 2026B-43873-ALaPorte124.50$85.00$65.504RIETH-RILEY CONSTRUCTION CO., INC.INDOT
Latest INDOT contracts carrying Overlay dam

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy