QC/QA-HMA, 3, 64, BASE, 19.0 mm unit price, Indiana
Low bidders on INDOT contracts carried a median of $117.27 per TON for item 401-07424, qc/qa-hma, 3, 64, base, 19.0 mm, from 12 JAN 2022 to 14 AUG 2024, across 94 low bids. Half of all 298 bids fell between $95.00 and $185.00.
- Owner
- Indiana DOT
- Item
- 401-07424
- Unit
- TON
- Latest letting
- 14 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 35 | 35 | $110.00 | 108 | $111.28 |
| 2023 | 44 | 44 | $122.88 | 139 | $122.00 |
| 2024 | 15 | 15 | $109.00 | 51 | $117.89 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Seymour | 27 | $145.00 | 100 | $162.50 |
| Vincennes | 16 | $131.50 | 53 | $134.00 |
| Crawfordsville | 15 | $112.00 | 48 | $109.23 |
| Greenfield | 16 | $106.50 | 46 | $103.97 |
| LaPorte | 11 | $100.00 | 32 | $100.00 |
| Fort Wayne | 8 | $108.00 | 16 | $106.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 10 to 135 | 23 | $218.00 |
| 156 to 546 | 24 | $132.00 |
| 562 to 2,706 | 23 | $100.00 |
| 3,197 to 31,895 | 24 | $93.12 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 14 AUG 2024 | R-42522-A | Crawfordsville | 1,465 | $143.51 | $143.51 | 3 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 14 AUG 2024 | R-43292-A | Seymour | 40 | $220.00 | $220.00 | 9 | PAUL H ROHE COMPANY INC | INDOT |
| 10 JUL 2024 | R-42252-A | Crawfordsville | 1,699 | $100.00 | $100.00 | 2 | MILESTONE CONTRACTORS LP | INDOT |
| 09 MAY 2024 | R-41802-A | Seymour | 992 | $91.00 | $91.00 | 3 | MAC CONSTRUCTION & EXCAVATING INC | INDOT |
| 09 MAY 2024 | B-41467-A | Seymour | 24 | $186.00 | $189.50 | 3 | FORCE CONSTRUCTION CO INC | INDOT |
| 10 APR 2024 | R-42616-B | Greenfield | 4,608 | $82.00 | $82.00 | 3 | GRADEX INC | INDOT |
| 10 APR 2024 | B-42241-A | Crawfordsville | 279 | $109.00 | $109.00 | 5 | CRACKERS DEMO LLC | INDOT |
| 13 MAR 2024 | B-41846-A | Fort Wayne | 8,844 | $117.89 | $118.94 | 2 | RIETH RILEY CONSTRUCTION | INDOT |
| 15 FEB 2024 | R-42426-A | Seymour | 7,815 | $83.00 | $83.00 | 3 | CRIDER & CRIDER INC | INDOT |
| 15 FEB 2024 | R-45025-A | Greenfield | 771 | $107.00 | $104.00 | 4 | CALUMET CIVIL CONTRACTORS INC | INDOT |
| 15 FEB 2024 | B-42341-A | Greenfield | 29 | $187.17 | $550.00 | 3 | OLCO INC | INDOT |
| 18 JAN 2024 | R-41862-A | Seymour | 14,796 | $78.25 | $78.25 | 5 | MILESTONE CONTRACTORS LP | INDOT |
| 18 JAN 2024 | R-42620-A | LaPorte | 3,752 | $91.00 | $91.00 | 3 | RIETH RILEY CONSTRUCTION | INDOT |
| 18 JAN 2024 | R-44898-B | Vincennes | 562 | $226.00 | $226.00 | 2 | J B I CONSTRUCTION INC | INDOT |
| 18 JAN 2024 | B-44203-A | Greenfield | 80 | $540.00 | $540.00 | 1 | PONTEM CONTRACTORS INC | INDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.
How these prices were read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way