Structure, manhole, reconstructed unit price, Indiana
Low bidders on INDOT contracts carried a median of $1,300.00 per LFT for item 720-45605, structure, manhole, reconstructed, over the 24 months to 05 NOV 2026, across 11 low bids. Half of all 45 bids fell between $1,000.00 and $1,700.00.
- Owner
- Indiana DOT
- Item
- 720-45605
- Unit
- LFT
- Latest letting
- 05 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 13 | 13 | $1,000.00 | 38 | $1,000.00 |
| 2023 | 14 | 14 | $902.50 | 31 | $1,050.00 |
| 2024 | 14 | 14 | $1,150.00 | 58 | $1,200.00 |
| 2025 | 6 | 6 | $1,600.00 | 21 | $1,400.00 |
| 2026 | 3 | 3 | $1,000.00 | 14 | $1,144.28 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 05 NOV 2026 | R-42227-A | Greenfield | 6 | $1,216.32 | $1,216.32 | 7 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 07 OCT 2026 | R-44109-A | LaPorte | 4 | $1,000.00 | $1,000.00 | 4 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 11 FEB 2026 | R-45152-A | Vincennes | 32 | $700.00 | $700.00 | 3 | RAGLE, INC/E & B PAVING LLC J/V | INDOT |
| 10 DEC 2025 | R-42000-A | Fort Wayne | 26 | $1,700.00 | $1,700.00 | 4 | HRP CONSTRUCTION INC | INDOT |
| 10 DEC 2025 | B-40311-A | Seymour | 22 | $1,300.00 | $1,400.00 | 6 | MILESTONE CONTRACTORS LP | INDOT |
| 10 SEP 2025 | R-43800-A | Fort Wayne | 6 | $1,944.79 | $1,522.39 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 09 JUL 2025 | R-43185-A | Fort Wayne | 14 | $3,878.06 | $1,300.00 | 4 | E & B PAVING LLC | INDOT |
| 12 FEB 2025 | R-42202-A | Greenfield | 3 | $1,500.00 | $1,400.00 | 2 | MORPHEY CONSTRUCTION INC. | INDOT |
| 22 JAN 2025 | R-41481-A | Seymour | 82 | $1,200.00 | $1,122.80 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 11 DEC 2024 | R-41395-A | Fort Wayne | 4 | $1,987.08 | $1,373.54 | 4 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 14 NOV 2024 | R-37909-A | Crawfordsville | 9 | $660.43 | $1,025.00 | 6 | GRADEX INC | INDOT |
| 09 OCT 2024 | R-41674-A | Greenfield | 4 | $985.80 | $985.80 | 7 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 09 OCT 2024 | R-42585-A | Fort Wayne | 11 | $4,127.31 | $2,563.66 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 14 AUG 2024 | R-43271-A | Fort Wayne | 12 | $1,300.00 | $2,150.00 | 2 | BROOKS CONSTRUCTION COMPANY INC | INDOT |
| 10 JUL 2024 | R-41772-A | Vincennes | 57 | $600.00 | $545.00 | 6 | BLANKENBERGER BROTHERS INC | INDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.
How these prices were read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.