Cable-no. 14/5C unit price, Kentucky
Low bidders on KYTC contracts carried a median of $2.02 per LF for cable-no. 14/5c, from 22 NOV 2019 to 22 AUG 2024, across 105 low bids. Half of all 227 bids fell between $1.50 and $3.00.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- LF
- Latest letting
- 22 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 1 | 1 | $1.25 | 3 | $1.25 |
| 2020 | 14 | 14 | $1.75 | 43 | $2.00 |
| 2021 | 22 | 22 | $1.92 | 62 | $2.00 |
| 2022 | 44 | 45 | $2.50 | 60 | $2.67 |
| 2023 | 15 | 15 | $1.88 | 34 | $1.80 |
| 2024 | 8 | 8 | $2.35 | 25 | $2.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 25 | $2.00 | 62 | $2.06 |
| District 6 | 14 | $2.52 | 39 | $2.40 |
| District 7 | 19 | $2.02 | 26 | $2.00 |
| District 4 | 6 | $2.04 | 24 | $2.05 |
| District 9 | 6 | $2.50 | 16 | $3.56 |
| District 12 | 5 | $3.00 | 13 | $2.00 |
| District 1 | 7 | $1.88 | 10 | $1.88 |
| District 8 | 6 | $2.46 | 9 | $2.02 |
| District 10 | 3 | $2.00 | 8 | $2.51 |
| District 2 | 5 | $1.39 | 8 | $3.83 |
| District 11 | 5 | $1.00 | 7 | $1.50 |
| District 3 | 4 | $2.00 | 5 | $2.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 35 to 680 | 26 | $2.23 |
| 680 to 1,720 | 26 | $2.45 |
| 1,750 to 3,730 | 26 | $2.01 |
| 3,760 to 14,550 | 27 | $1.60 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 AUG 2024 | 24-1011 | District 11 | 4,725 | $2.25 | $2.25 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 AUG 2024 | 24-1110 | District 10 | 680 | $2.51 | $2.58 | 6 | WALKER CONSTRUCTION & MATERIALS LLC | KYTC |
| 18 JUL 2024 | 24-1313 | District 6 | 60 | $1.50 | $1.50 | 4 | RIEGLER BLACKTOP INC | KYTC |
| 18 JUL 2024 | 24-4403 | District 5 | 320 | $2.45 | $2.45 | 1 | DAVIS H ELLIOT CONSTRUCTION COMPANY INC | KYTC |
| 20 JUN 2024 | 24-1107 | District 4 | 2,275 | $2.70 | $2.50 | 5 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 23 MAY 2024 | 24-1105 | District 5 | 2,203 | $2.13 | $2.13 | 6 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 25 APR 2024 | 24-4401 | District 7 | 1,010 | $2.68 | $2.68 | 1 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 21 MAR 2024 | 24-1306 | District 10 | 6,140 | $1.35 | $1.35 | 1 | TRITON CONSTRUCTION INC | KYTC |
| 16 NOV 2023 | 23-1109 | District 5 | 425 | $1.26 | $1.73 | 5 | FLYNN BROTHERS CONTRACTING INC | KYTC |
| 26 OCT 2023 | 23-1339 | District 5 | 11,117 | $1.60 | $1.60 | 5 | CLEARY CONSTRUCTION INC | KYTC |
| 26 OCT 2023 | 23-4107 | District 8 | 2,450 | $2.02 | $2.02 | 3 | LOUISVILLE PAVING COMPANY INC | KYTC |
| 26 OCT 2023 | 23-4418 | District 7 | 3,920 | $2.07 | $2.07 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 26 OCT 2023 | 23-1342 | District 5 | 9,651 | $2.71 | $2.71 | 4 | FLYNN BROTHERS CONTRACTING INC | KYTC |
| 24 AUG 2023 | 23-4412 | District 7 | 3,920 | $1.26 | $1.26 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 JUN 2023 | 23-1032 | District 2 | 14,550 | $1.35 | $3.00 | 3 | YAGER MATERIALS CORP | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.