Class a concrete for signs unit price, Kentucky
Low bidders on KYTC contracts carried a median of $1,025.00 per CY for class a concrete for signs, from 24 JUL 2020 to 26 SEP 2024, across 97 low bids. Half of all 175 bids fell between $700.00 and $1,843.88.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- CY
- Latest letting
- 26 SEP 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 8 | $550.00 | 25 | $650.00 |
| 2021 | 14 | 13 | $603.69 | 32 | $700.00 |
| 2022 | 27 | 27 | $1,000.00 | 36 | $1,000.00 |
| 2023 | 41 | 41 | $1,500.00 | 60 | $1,500.00 |
| 2024 | 8 | 8 | $2,000.00 | 22 | $2,550.47 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 15 | $1,500.00 | 37 | $1,720.34 |
| District 6 | 12 | $1,035.00 | 25 | $1,050.00 |
| District 7 | 16 | $1,000.00 | 21 | $816.00 |
| District 10 | 5 | $1,000.00 | 17 | $950.00 |
| District 8 | 7 | $750.00 | 15 | $700.00 |
| District 3 | 9 | $1,000.00 | 13 | $1,142.32 |
| District 9 | 5 | $750.00 | 11 | $750.00 |
| District 1 | 7 | $1,005.24 | 10 | $1,002.62 |
| District 12 | 8 | $1,500.00 | 8 | $1,500.00 |
| District 4 | 5 | $1,200.00 | 7 | $1,025.63 |
| District 2 | 5 | $1,000.00 | 7 | $1,260.23 |
| District 11 | 3 | $1,000.00 | 4 | $1,000.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 0.25 to 1.07 | 24 | $1,500.00 |
| 1.25 to 6.75 | 24 | $975.00 |
| 7.08 to 24.50 | 24 | $1,000.00 |
| 25 to 737.20 | 25 | $1,200.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 SEP 2024 | 24-4202 | District 7 | 6.75 | $816.00 | $808.00 | 2 | THE ALLEN COMPANY INC | KYTC |
| 22 AUG 2024 | 24-1315 | District 3 | 0.50 | $2,000.00 | $5,834.63 | 2 | CLEARY CONSTRUCTION INC | KYTC |
| 22 AUG 2024 | 24-1110 | District 10 | 0.46 | $2,000.00 | $3,587.91 | 6 | WALKER CONSTRUCTION & MATERIALS LLC | KYTC |
| 18 JUL 2024 | 24-1313 | District 6 | 2.20 | $2,000.00 | $4,504.45 | 4 | RIEGLER BLACKTOP INC | KYTC |
| 21 MAR 2024 | 24-1005 | District 7 | 17.80 | $2,870.99 | $2,870.99 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 21 MAR 2024 | 24-4300 | District 7 | 2 | $793.77 | $793.77 | 2 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 21 MAR 2024 | 24-1301 | District 1 | 1 | $1,396.40 | $1,396.40 | 1 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 22 FEB 2024 | 24-1305 | District 6 | 35.10 | $2,695.00 | $2,550.47 | 4 | EATON ASPHALT PAVING CO INC | KYTC |
| 14 DEC 2023 | 23-4009 | District 9 | 25.50 | $1,000.00 | $1,000.00 | 1 | GEORGE B STONE CO LLC | KYTC |
| 14 DEC 2023 | 23-4012 | District 12 | 17 | $1,200.00 | $1,200.00 | 1 | GEORGE B STONE CO LLC | KYTC |
| 16 NOV 2023 | 23-4017 | District 5 | 126.50 | $1,500.00 | $1,500.00 | 1 | EDEN FENCE INC | KYTC |
| 16 NOV 2023 | 23-4018 | District 6 | 64.50 | $1,050.00 | $1,050.00 | 1 | GEORGE B STONE CO LLC | KYTC |
| 16 NOV 2023 | 23-4504 | District 1 | 0.50 | $1,000.00 | $1,000.00 | 1 | EDEN FENCE INC | KYTC |
| 16 NOV 2023 | 23-1109 | District 5 | 0.46 | $3,000.00 | $3,000.00 | 5 | FLYNN BROTHERS CONTRACTING INC | KYTC |
| 26 OCT 2023 | 23-1041 | District 12 | 23.60 | $2,000.00 | $2,000.00 | 1 | MOUNTAIN ENTERPRISES INC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.