Delineator for guardrail mono directional white unit price, Kentucky
Low bidders on KYTC contracts carried a median of $16.18 per EACH for delineator for guardrail mono directional white, over the 24 months to 22 OCT 2026, across 1 low bids. Half of all 1 bids fell between $16.18 and $16.18.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- EACH
- Latest letting
- 24 OCT 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 1 | 1 | $5.62 | 4 | $6.50 |
| 2020 | 22 | 22 | $10.00 | 63 | $10.00 |
| 2021 | 42 | 42 | $9.84 | 87 | $10.00 |
| 2022 | 57 | 57 | $12.00 | 76 | $12.00 |
| 2023 | 39 | 39 | $13.71 | 62 | $13.73 |
| 2024 | 13 | 13 | $15.97 | 34 | $16.09 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 19 | $12.50 | 59 | $12.50 |
| District 2 | 27 | $11.05 | 43 | $10.80 |
| District 6 | 15 | $12.07 | 41 | $12.00 |
| District 7 | 28 | $12.25 | 37 | $12.25 |
| District 9 | 14 | $12.00 | 32 | $12.00 |
| District 4 | 16 | $10.00 | 30 | $10.00 |
| District 11 | 13 | $14.00 | 21 | $15.00 |
| District 12 | 10 | $15.00 | 19 | $12.00 |
| District 3 | 15 | $9.37 | 15 | $9.37 |
| District 1 | 8 | $9.00 | 14 | $10.00 |
| District 10 | 5 | $12.00 | 9 | $12.00 |
| District 8 | 4 | $10.00 | 6 | $10.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 12 | 43 | $12.00 |
| 12 to 37 | 44 | $12.40 |
| 40 to 144 | 43 | $10.00 |
| 144 to 1,921 | 44 | $12.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 OCT 2024 | 24-1111 | District 2 | 18 | $16.18 | $16.18 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 26 SEP 2024 | 24-4202 | District 7 | 46 | $12.24 | $13.87 | 2 | THE ALLEN COMPANY INC | KYTC |
| 22 AUG 2024 | 24-1011 | District 11 | 12 | $15.36 | $15.36 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 18 JUL 2024 | 24-5357 | District 5 | 4 | $16.58 | $18.29 | 4 | E AND B PAVING LLC | KYTC |
| 18 JUL 2024 | 24-1108 | District 3 | 132 | $15.97 | $15.97 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 20 JUN 2024 | 24-1106 | District 2 | 15 | $18.13 | $18.13 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 23 MAY 2024 | 24-1105 | District 5 | 13 | $15.36 | $15.36 | 6 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 25 APR 2024 | 24-5345 | District 9 | 30 | $15.00 | $16.50 | 4 | WALKER CONSTRUCTION & MATERIALS LLC | KYTC |
| 25 APR 2024 | 24-4401 | District 7 | 2 | $18.38 | $18.38 | 1 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 25 APR 2024 | 24-2985 | District 7 | 3 | $15.36 | $15.36 | 2 | HALL CONTRACTING OF KENTUCKY INC | KYTC |
| 21 MAR 2024 | 24-1005 | District 7 | 68 | $15.36 | $15.36 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 21 MAR 2024 | 24-5341 | District 11 | 9 | $20.00 | $18.50 | 6 | INTECH CONTRACTING LLC | KYTC |
| 22 FEB 2024 | 24-1305 | District 6 | 108 | $16.00 | $15.98 | 4 | EATON ASPHALT PAVING CO INC | KYTC |
| 14 DEC 2023 | 23-1112 | District 5 | 240 | $15.84 | $15.84 | 3 | LOUISVILLE PAVING COMPANY INC | KYTC |
| 14 DEC 2023 | 23-1047 | District 10 | 317 | $18.00 | $18.00 | 2 | HINKLE CONTRACTING COMPANY LLC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way