Fused connector kit unit price, Kentucky

Low bidders on KYTC contracts carried a median of $200.00 per EACH for fused connector kit, from 22 NOV 2019 to 26 SEP 2024, across 74 low bids. Half of all 142 bids fell between $150.00 and $255.72.

Owner
Kentucky Transportation Cabinet
Item
No code published
Unit
EACH
Latest letting
26 SEP 2024
$200.00Low bidder's median, per EACH
$195.00Median of all bids, per EACH
65Contracts in the window

By year of letting

Fused connector kit, KYTC: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201911$150.003$150.00
20201010$184.0020$167.05
20211014$240.5034$237.78
20222122$250.0033$250.00
20231215$187.5130$188.21
20241112$151.5022$150.00
Fused connector kit, KYTC: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Fused connector kit, KYTC: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 517$200.0044$188.21
District 610$186.5020$105.00
District 713$153.0018$151.50
District 111$190.0017$200.00
District 118$240.5014$238.00
District 123$250.008$250.00
District 44$226.128$238.77
Fused connector kit, KYTC: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Fused connector kit, KYTC: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
2 to 1118$250.00
11 to 2419$250.00
24 to 3918$151.50
40 to 14019$150.00
Fused connector kit, KYTC: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest KYTC contracts carrying Fused connector kit
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
26 SEP 202424-1014District 732$153.00$151.502THE ALLEN COMPANY INCKYTC
22 AUG 202424-1013District 124$268.01$209.002MOUNTAIN ENTERPRISES INCKYTC
22 AUG 202424-1011District 1138$150.00$150.001L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
18 JUL 202424-1010District 732$210.00$210.001THE ALLEN COMPANY INCKYTC
21 MAR 202424-1306District 1063$150.00$150.001TRITON CONSTRUCTION INCKYTC
21 MAR 202424-1306District 1096$150.00$150.001TRITON CONSTRUCTION INCKYTC
21 MAR 202424-1005District 760$125.00$125.001L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
21 MAR 202424-1007District 484$348.14$348.143HAYDON MATERIALS LLCKYTC
21 MAR 202424-4300District 721$150.00$150.002L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
21 MAR 202424-1301District 18$200.00$200.001JIM SMITH CONTRACTING COMPANY LLCKYTC
22 FEB 202424-1002District 426$202.24$202.243SCOTTY'S CONTRACTING & STONE LLCKYTC
22 FEB 202424-1305District 642$111.00$107.974EATON ASPHALT PAVING CO INCKYTC
26 OCT 202323-1340District 721$342.27$342.271L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
26 OCT 202323-1341District 7140$187.51$187.511L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTIONKYTC
26 OCT 202323-1339District 549$238.73$238.735CLEARY CONSTRUCTION INCKYTC
Latest KYTC contracts carrying Fused connector kit

Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.

How these prices were read

KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy