Pave marking-thermo comb arrow unit price, Kentucky
Low bidders on KYTC contracts carried a median of $172.50 per EACH for pave marking-thermo comb arrow, over the 24 months to 22 OCT 2026, across 4 low bids. Half of all 5 bids fell between $150.00 and $195.00.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- EACH
- Latest letting
- 24 OCT 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2019 | 5 | 5 | $150.00 | 7 | $150.00 |
| 2020 | 55 | 55 | $145.00 | 160 | $150.00 |
| 2021 | 82 | 83 | $155.00 | 172 | $166.50 |
| 2022 | 99 | 102 | $165.00 | 175 | $165.00 |
| 2023 | 77 | 78 | $185.00 | 132 | $185.00 |
| 2024 | 56 | 56 | $154.25 | 124 | $165.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 56 | $175.00 | 189 | $175.00 |
| District 6 | 50 | $140.00 | 123 | $148.00 |
| District 7 | 60 | $140.00 | 87 | $140.00 |
| District 4 | 27 | $250.00 | 69 | $250.00 |
| District 3 | 37 | $267.76 | 64 | $270.63 |
| District 11 | 34 | $150.00 | 49 | $150.00 |
| District 9 | 22 | $140.00 | 43 | $140.00 |
| District 2 | 23 | $225.00 | 39 | $230.00 |
| District 8 | 22 | $250.00 | 35 | $145.00 |
| District 1 | 21 | $200.00 | 34 | $200.00 |
| District 10 | 18 | $150.00 | 23 | $150.00 |
| District 12 | 9 | $175.00 | 15 | $175.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 94 | $150.00 |
| 2 to 3 | 95 | $170.00 |
| 3 to 5 | 95 | $175.00 |
| 5 to 97 | 95 | $150.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 OCT 2024 | 24-2353 | District 10 | 2 | $150.00 | $150.00 | 1 | MOUNTAIN ENTERPRISES INC | KYTC |
| 24 OCT 2024 | 24-2318 | District 2 | 2 | $240.00 | $240.00 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 24 OCT 2024 | 24-2219 | District 7 | 1 | $140.00 | $145.00 | 2 | MAC CONSTRUCTION & EXCAVATING INC | KYTC |
| 24 OCT 2024 | 24-2329 | District 1 | 5 | $195.00 | $195.00 | 1 | ROGERS GROUP INC | KYTC |
| 26 SEP 2024 | 24-2305 | District 5 | 3 | $165.00 | $165.00 | 4 | HALL CONTRACTING OF KENTUCKY INC | KYTC |
| 26 SEP 2024 | 24-2303 | District 5 | 4 | $125.00 | $125.00 | 4 | MAGO CONSTRUCTION COMPANY LLC | KYTC |
| 26 SEP 2024 | 24-2209 | District 8 | 4 | $300.00 | $300.00 | 1 | GADDIE-SHAMROCK LLC | KYTC |
| 26 SEP 2024 | 24-2298 | District 4 | 3 | $300.00 | $300.00 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 26 SEP 2024 | 24-2314 | District 6 | 10 | $140.00 | $140.00 | 2 | RIEGLER BLACKTOP INC | KYTC |
| 22 AUG 2024 | 24-1011 | District 11 | 5 | $150.00 | $150.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 AUG 2024 | 24-1315 | District 3 | 20 | $250.00 | $250.00 | 2 | CLEARY CONSTRUCTION INC | KYTC |
| 22 AUG 2024 | 24-2099 | District 10 | 2 | $195.00 | $195.00 | 1 | MOUNTAIN ENTERPRISES INC | KYTC |
| 22 AUG 2024 | 24-2260 | District 6 | 1 | $140.00 | $144.20 | 2 | RIEGLER BLACKTOP INC | KYTC |
| 22 AUG 2024 | 24-2259 | District 6 | 2 | $140.00 | $144.20 | 2 | RIEGLER BLACKTOP INC | KYTC |
| 22 AUG 2024 | 24-2234 | District 6 | 1 | $175.00 | $175.00 | 3 | MAGO CONSTRUCTION COMPANY LLC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.