Pave striping-perm paint-4 in unit price, Kentucky
Low bidders on KYTC contracts carried a median of $0.29 per LF A for pave striping-perm paint-4 in, over the 24 months to 22 OCT 2026, across 106 low bids. Half of all 269 bids fell between $0.24 and $1.50.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- LF A
- Latest letting
- 24 APR 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 1 | 1 | $0.13 | 4 | $0.12 |
| 2024 | 41 | 48 | $0.30 | 142 | $0.36 |
| 2025 | 53 | 58 | $0.28 | 127 | $0.34 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 15 | $0.26 | 62 | $0.47 |
| District 4 | 11 | $1.20 | 39 | $1.00 |
| District 2 | 14 | $0.35 | 38 | $1.25 |
| District 7 | 9 | $0.29 | 29 | $2.00 |
| District 8 | 8 | $0.25 | 18 | $0.30 |
| District 9 | 5 | $0.20 | 15 | $0.22 |
| District 11 | 12 | $0.24 | 14 | $0.26 |
| District 6 | 6 | $0.18 | 13 | $0.18 |
| District 12 | 7 | $0.25 | 12 | $0.26 |
| District 1 | 7 | $0.20 | 12 | $0.35 |
| District 10 | 7 | $0.20 | 9 | $0.23 |
| District 3 | 5 | $0.32 | 8 | $0.32 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF A) | Low bids | Low-bid median |
|---|---|---|
| 12 to 1,590 | 26 | $2.00 |
| 1,590 to 20,310 | 27 | $0.31 |
| 24,520 to 50,000 | 26 | $0.23 |
| 54,122 to 360,000 | 27 | $0.24 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 APR 2025 | 25-5376 | District 4 | 468 | $1.50 | $1.58 | 4 | FREDERICK & MAY CONSTRUCTION CO | KYTC |
| 24 APR 2025 | 25-1305 | District 1 | 3,856 | $0.50 | $0.50 | 2 | HARPER CONSTRUCTION LLC | KYTC |
| 24 APR 2025 | 25-2151 | District 6 | 24,520 | $0.28 | $0.23 | 2 | RIEGLER BLACKTOP INC | KYTC |
| 24 APR 2025 | 25-3024 | District 7 | 17,500 | $0.20 | $0.20 | 1 | LEXINGTON QUARRY COMPANY | KYTC |
| 24 APR 2025 | 25-3022 | District 2 | 30,000 | $0.33 | $0.33 | 2 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 24 APR 2025 | 25-2202 | District 10 | 148,010 | $0.15 | $0.15 | 1 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 24 APR 2025 | 25-2973 | District 5 | 12 | $10.00 | $6.00 | 2 | INTECH CONTRACTING LLC | KYTC |
| 24 APR 2025 | 25-3025 | District 11 | 134,515 | $0.24 | $0.24 | 1 | MOUNTAIN ENTERPRISES INC | KYTC |
| 24 APR 2025 | 25-3026 | District 11 | 39,700 | $0.25 | $0.25 | 1 | THE ALLEN COMPANY INC | KYTC |
| 24 APR 2025 | 25-3027 | District 11 | 71,070 | $0.24 | $0.24 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 20 MAR 2025 | 25-1104 | District 8 | 2,552 | $0.28 | $0.29 | 2 | RAME CONTRACTING LLC | KYTC |
| 20 MAR 2025 | 25-1105 | District 1 | 3,750 | $0.12 | $0.12 | 1 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 20 MAR 2025 | 25-4202 | District 1 | 2,600 | $0.75 | $0.75 | 2 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 20 MAR 2025 | 25-2149 | District 2 | 55,740 | $0.33 | $0.33 | 1 | SCOTTY'S CONTRACTING & STONE LLC | KYTC |
| 20 MAR 2025 | 25-2077 | District 6 | 166,265 | $0.14 | $0.18 | 5 | HINKLE CONTRACTING COMPANY LLC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.