Piles-steel HP14X89 unit price, Kentucky
Low bidders on KYTC contracts carried a median of $134.00 per LF for piles-steel hp14x89, over the 24 months to 22 OCT 2026, across 1 low bids. Half of all 2 bids fell between $119.75 and $129.25.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- LF
- Latest letting
- 24 OCT 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 12 | $70.00 | 46 | $81.50 |
| 2021 | 4 | 7 | $125.00 | 23 | $120.00 |
| 2022 | 15 | 20 | $162.50 | 60 | $190.00 |
| 2023 | 18 | 18 | $127.50 | 57 | $166.00 |
| 2024 | 18 | 22 | $120.00 | 82 | $150.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 12 | 20 | $194.00 | 85 | $177.66 |
| District 1 | 16 | $81.52 | 36 | $85.44 |
| District 9 | 6 | $125.00 | 23 | $115.00 |
| District 4 | 5 | $118.00 | 21 | $115.00 |
| District 10 | 4 | $136.00 | 20 | $172.00 |
| District 8 | 5 | $113.00 | 20 | $148.50 |
| District 2 | 6 | $106.53 | 18 | $118.00 |
| District 11 | 4 | $152.00 | 15 | $167.06 |
| District 6 | 4 | $170.25 | 12 | $164.50 |
| District 7 | 4 | $169.00 | 10 | $173.50 |
| District 3 | 4 | $132.50 | 4 | $132.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 68 to 206.50 | 19 | $203.00 |
| 230 to 535 | 20 | $127.50 |
| 580 to 1,510 | 20 | $112.57 |
| 1,909 to 9,225 | 20 | $90.55 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 OCT 2024 | 24-1318 | District 2 | 739 | $134.00 | $124.50 | 2 | SCOTT AND MURPHY INC | KYTC |
| 22 AUG 2024 | 24-1013 | District 12 | 1,460 | $150.00 | $145.00 | 2 | MOUNTAIN ENTERPRISES INC | KYTC |
| 22 AUG 2024 | 24-1011 | District 11 | 299 | $150.00 | $150.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 AUG 2024 | 24-1011 | District 11 | 356 | $154.00 | $154.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 20 JUN 2024 | 24-5354 | District 1 | 6,614 | $94.83 | $104.91 | 2 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 20 JUN 2024 | 24-5355 | District 1 | 1,467 | $80.00 | $87.78 | 2 | HAL COFFEY CONTRACTING LLC | KYTC |
| 20 JUN 2024 | 24-5355 | District 1 | 7,610 | $85.00 | $90.28 | 2 | HAL COFFEY CONTRACTING LLC | KYTC |
| 20 JUN 2024 | 24-5355 | District 1 | 1,078 | $80.00 | $87.78 | 2 | HAL COFFEY CONTRACTING LLC | KYTC |
| 23 MAY 2024 | 24-5350 | District 11 | 125 | $170.00 | $167.06 | 7 | IRVINE CONTRACTING LIMITED LIABILITY COMPANY | KYTC |
| 23 MAY 2024 | 24-5349 | District 4 | 104 | $167.00 | $191.50 | 6 | GALUSHA CONTRACTING LLC | KYTC |
| 25 APR 2024 | 24-2987 | District 12 | 176 | $150.00 | $173.00 | 6 | KAY & KAY CONTRACTING LLC | KYTC |
| 25 APR 2024 | 24-5344 | District 1 | 2,098 | $96.25 | $105.62 | 2 | JIM SMITH CONTRACTING COMPANY LLC | KYTC |
| 25 APR 2024 | 24-5345 | District 9 | 1,134 | $125.00 | $121.50 | 4 | WALKER CONSTRUCTION & MATERIALS LLC | KYTC |
| 25 APR 2024 | 24-1008 | District 7 | 68 | $225.00 | $209.44 | 3 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 21 MAR 2024 | 24-5338 | District 2 | 9,225 | $102.22 | $108.61 | 2 | SCOTT AND MURPHY INC | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.