Standard curb and gutter unit price, Kentucky
Low bidders on KYTC contracts carried a median of $43.31 per LF for standard curb and gutter, from 24 JAN 2020 to 26 SEP 2024, across 124 low bids. Half of all 270 bids fell between $28.51 and $55.00.
- Owner
- Kentucky Transportation Cabinet
- Item
- No code published
- Unit
- LF
- Latest letting
- 26 SEP 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 13 | 14 | $33.02 | 42 | $26.72 |
| 2021 | 22 | 23 | $35.00 | 66 | $34.00 |
| 2022 | 35 | 35 | $42.00 | 48 | $40.00 |
| 2023 | 28 | 28 | $53.28 | 48 | $47.14 |
| 2024 | 24 | 24 | $53.75 | 66 | $45.03 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 16 | $38.64 | 48 | $36.92 |
| District 6 | 12 | $29.54 | 43 | $28.25 |
| District 4 | 16 | $44.12 | 34 | $43.20 |
| District 7 | 20 | $55.50 | 30 | $53.28 |
| District 2 | 12 | $38.00 | 26 | $38.16 |
| District 11 | 14 | $40.00 | 18 | $40.00 |
| District 3 | 8 | $44.50 | 15 | $38.00 |
| District 9 | 5 | $52.50 | 15 | $52.50 |
| District 10 | 4 | $63.50 | 14 | $41.39 |
| District 12 | 8 | $63.05 | 14 | $59.64 |
| District 8 | 5 | $36.00 | 8 | $36.00 |
| District 1 | 4 | $37.47 | 5 | $35.79 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 5 to 167 | 31 | $60.00 |
| 167 to 625 | 31 | $50.00 |
| 655 to 2,937 | 31 | $38.00 |
| 3,107 to 29,346 | 31 | $29.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 SEP 2024 | 24-4106 | District 11 | 101.54 | $105.00 | $105.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 26 SEP 2024 | 24-5361 | District 2 | 60 | $60.00 | $60.00 | 3 | GALUSHA CONTRACTING LLC | KYTC |
| 22 AUG 2024 | 24-1011 | District 11 | 93 | $150.00 | $150.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 22 AUG 2024 | 24-1315 | District 3 | 625 | $26.40 | $26.40 | 2 | CLEARY CONSTRUCTION INC | KYTC |
| 22 AUG 2024 | 24-1009 | District 12 | 1,657 | $32.44 | $32.50 | 3 | FREDERICK & MAY CONSTRUCTION CO | KYTC |
| 22 AUG 2024 | 24-1110 | District 10 | 686 | $57.00 | $44.25 | 6 | WALKER CONSTRUCTION & MATERIALS LLC | KYTC |
| 18 JUL 2024 | 24-1313 | District 6 | 8,531 | $30.00 | $30.00 | 4 | RIEGLER BLACKTOP INC | KYTC |
| 18 JUL 2024 | 24-2268 | District 9 | 916 | $52.50 | $76.77 | 2 | BLUEGRASS CONTRACTING CORPORATION | KYTC |
| 18 JUL 2024 | 24-2050 | District 9 | 280 | $60.00 | $69.00 | 5 | FREDERICK & MAY CONSTRUCTION CO | KYTC |
| 18 JUL 2024 | 24-1012 | District 12 | 264 | $64.60 | $64.60 | 1 | MOUNTAIN ENTERPRISES INC | KYTC |
| 20 JUN 2024 | 24-1107 | District 4 | 464 | $42.28 | $42.28 | 5 | HINKLE CONSTRUCTION SERVICES LLC | KYTC |
| 20 JUN 2024 | 24-5352 | District 4 | 80 | $55.00 | $100.00 | 3 | M & M SERVICES CO INC | KYTC |
| 20 JUN 2024 | 24-4103 | District 8 | 365 | $36.00 | $36.00 | 1 | HINKLE CONTRACTING COMPANY LLC | KYTC |
| 20 JUN 2024 | 24-2142 | District 7 | 46 | $125.00 | $125.00 | 1 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
| 23 MAY 2024 | 24-1105 | District 5 | 1,470 | $31.42 | $31.42 | 6 | L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION | KYTC |
Filter this item by your own quantity, district and period, or check your price against it, in the KYTC explorer.
How these prices were read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are KYTC's own: this item is compared with KYTC contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way