15 in. pipe group c unit price, Missouri
Low bidders on MoDOT contracts carried a median of $77.75 per LF for item 7250415, 15 in. pipe group c, over the 24 months to 16 OCT 2026, across 24 low bids. Half of all 87 bids fell between $62.73 and $109.10.
- Owner
- Missouri DOT
- Item
- 7250415
- Unit
- LF
- Latest letting
- 16 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 8 | $52.48 | 24 | $57.98 |
| 2021 | 14 | 15 | $50.00 | 48 | $53.50 |
| 2022 | 16 | 18 | $75.00 | 52 | $80.00 |
| 2023 | 7 | 6 | $73.50 | 17 | $70.00 |
| 2024 | 15 | 14 | $80.00 | 48 | $80.00 |
| 2025 | 10 | 11 | $80.00 | 40 | $80.00 |
| 2026 | 10 | 10 | $66.40 | 36 | $75.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Southwest | 6 | $83.83 | 25 | $85.00 |
| Southeast | 5 | $80.00 | 15 | $80.00 |
| Northeast | 5 | $70.00 | 14 | $71.50 |
| Northwest | 3 | $65.00 | 7 | $65.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 8 to 39 | 6 | $97.00 |
| 44 to 72 | 6 | $73.78 |
| 117 to 208 | 6 | $57.50 |
| 263 to 1,260 | 6 | $77.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 16 OCT 2026 | 261016-G11 | Southwest | 263 | $75.50 | $66.50 | 7 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 18 JUN 2026 | 260618-H03 | Southeast | 67 | $48.00 | $93.50 | 6 | Robertson Contractors, Inc. | MoDOT |
| 15 MAY 2026 | 260515-C14 | Kansas City | 8 | $309.20 | $194.00 | 3 | Realm Construction Inc. | MoDOT |
| 15 MAY 2026 | 260515-G01 | Southwest | 8 | $192.50 | $192.50 | 3 | Ti-Zack Concrete, LLC | MoDOT |
| 15 MAY 2026 | 260515-G06 | Southwest | 311 | $62.80 | $71.63 | 4 | Hartman and Company, Inc. | MoDOT |
| 17 APR 2026 | 260417-B02 | Northeast | 1,260 | $33.00 | $62.00 | 3 | Magruder Paving, LLC | MoDOT |
| 20 MAR 2026 | 260320-B04 | Northeast | 136 | $94.30 | $94.30 | 1 | Louis-Company, LLC | MoDOT |
| 20 FEB 2026 | 260220-A02 | Northwest | 50 | $24.33 | $67.96 | 4 | Decatur Bridge & Iron LLC | MoDOT |
| 20 FEB 2026 | 260220-B03 | Northeast | 117 | $70.00 | $103.75 | 2 | TB Dozing & Excavation, LLC | MoDOT |
| 20 FEB 2026 | 260220-H02 | Southeast | 205 | $40.00 | $40.00 | 3 | Pace Construction Company, LLC | MoDOT |
| 20 JUN 2025 | 250620-B01 | Northeast | 33 | $65.00 | $89.08 | 4 | Stanton Contracting, L.L.C. | MoDOT |
| 16 MAY 2025 | 250516-A03 | Northwest | 464 | $116.12 | $90.56 | 2 | Ti-Zack Concrete, LLC | MoDOT |
| 16 MAY 2025 | 250516-G02 | Southwest | 72 | $98.92 | $107.96 | 4 | Hartman and Company, Inc. | MoDOT |
| 16 MAY 2025 | 250516-G02 | Southwest | 44 | $82.56 | $105.00 | 4 | Hartman and Company, Inc. | MoDOT |
| 16 MAY 2025 | 250516-H08 | Southeast | 811 | $80.00 | $80.00 | 2 | H.R. Quadri Contractors, LLC | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.