6 in. concrete median strip unit price, Missouri
Low bidders on MoDOT contracts carried a median of $140.00 per SY for item 6083006, 6 in. concrete median strip, over the 24 months to 16 OCT 2026, across 47 low bids. Half of all 177 bids fell between $106.45 and $195.02.
- Owner
- Missouri DOT
- Item
- 6083006
- Unit
- SY
- Latest letting
- 16 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 4 | $101.25 | 12 | $110.92 |
| 2021 | 9 | 9 | $97.00 | 29 | $91.65 |
| 2022 | 14 | 14 | $125.50 | 31 | $131.00 |
| 2023 | 16 | 19 | $132.95 | 53 | $118.00 |
| 2024 | 12 | 11 | $125.00 | 47 | $125.00 |
| 2025 | 26 | 28 | $131.50 | 103 | $140.00 |
| 2026 | 14 | 14 | $164.00 | 45 | $176.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| St. Louis | 17 | $145.00 | 69 | $147.00 |
| Kansas City | 10 | $123.22 | 35 | $132.55 |
| Central | 7 | $142.33 | 25 | $125.00 |
| Southwest | 6 | $91.17 | 24 | $95.50 |
| Southeast | 3 | $148.01 | 13 | $206.00 |
| Northwest | 3 | $195.02 | 7 | $150.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 63.80 | 11 | $140.00 |
| 64.20 to 160.80 | 12 | $139.50 |
| 168.40 to 450 | 12 | $123.50 |
| 478 to 2,049.70 | 12 | $140.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 16 OCT 2026 | 261016-F03 | St. Louis | 191 | $152.00 | $137.50 | 4 | Pace Construction Company, LLC | MoDOT |
| 18 JUN 2026 | 260618-D01 | Central | 1 | $815.00 | $907.50 | 4 | Watson Concrete, Inc. | MoDOT |
| 18 JUN 2026 | 260618-F01 | St. Louis | 46.60 | $97.00 | $211.50 | 4 | Millstone Weber, LLC | MoDOT |
| 15 MAY 2026 | 260515-F01 | St. Louis | 492.50 | $176.00 | $293.50 | 3 | R. V. Wagner, Inc. | MoDOT |
| 15 MAY 2026 | 260515-F02 | St. Louis | 223 | $91.50 | $175.00 | 3 | Lamke Trenching & Excavating, Inc. | MoDOT |
| 17 APR 2026 | 260417-D03 | Central | 232 | $142.33 | $211.17 | 2 | Ti-Zack Concrete, LLC | MoDOT |
| 17 APR 2026 | 260417-G01 | Southwest | 450 | $51.15 | $87.30 | 4 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 20 MAR 2026 | 260320-A01 | Northwest | 63.80 | $195.02 | $195.02 | 1 | Ti-Zack Concrete, LLC | MoDOT |
| 20 MAR 2026 | 260320-F01 | St. Louis | 72.30 | $126.16 | $185.00 | 5 | Ti-Zack Concrete, LLC | MoDOT |
| 20 MAR 2026 | 260320-F02 | St. Louis | 2,049.70 | $150.00 | $150.00 | 3 | N.B. West Contracting Company | MoDOT |
| 20 MAR 2026 | 260320-H03 | Southeast | 6 | $950.00 | $705.00 | 2 | Gerstner Electric, Inc. | MoDOT |
| 20 FEB 2026 | 260220-C01 | Kansas City | 97.10 | $196.00 | $164.90 | 4 | Amino Bros. Co., Inc. | MoDOT |
| 20 FEB 2026 | 260220-C03 | Kansas City | 418.40 | $195.75 | $162.67 | 3 | Leavenworth Excavating & Equipment Company, Inc. | MoDOT |
| 20 FEB 2026 | 260220-D01 | Central | 88 | $230.50 | $197.90 | 3 | Watson Concrete, Inc. | MoDOT |
| 12 DEC 2025 | 251212-D02 | Central | 304 | $115.00 | $115.00 | 3 | Sam Gaines Construction, Inc. | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.