Cable, 12 awg 2 conductor unit price, Missouri
Low bidders on MoDOT contracts carried a median of $1.88 per LF for item 9028302, cable, 12 awg 2 conductor, over the 24 months to 16 OCT 2026, across 20 low bids. Half of all 72 bids fell between $1.40 and $2.40.
- Owner
- Missouri DOT
- Item
- 9028302
- Unit
- LF
- Latest letting
- 15 MAY 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $1.20 | 13 | $1.25 |
| 2021 | 3 | 3 | $1.55 | 8 | $1.50 |
| 2022 | 9 | 10 | $1.59 | 22 | $1.60 |
| 2023 | 11 | 12 | $2.00 | 42 | $2.00 |
| 2024 | 10 | 9 | $1.55 | 37 | $1.40 |
| 2025 | 11 | 12 | $1.88 | 44 | $1.85 |
| 2026 | 3 | 3 | $3.08 | 6 | $2.99 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| St. Louis | 7 | $1.33 | 29 | $1.33 |
| Southwest | 5 | $2.15 | 18 | $2.20 |
| Kansas City | 5 | $3.35 | 16 | $3.40 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 70 to 320 | 5 | $1.90 |
| 450 to 610 | 5 | $2.80 |
| 740 to 1,230 | 5 | $1.45 |
| 1,620 to 3,600 | 5 | $1.55 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 MAY 2026 | 260515-C14 | Kansas City | 970 | $3.35 | $3.35 | 3 | Realm Construction Inc. | MoDOT |
| 15 MAY 2026 | 260515-G02 | Southwest | 2,540 | $2.70 | $2.70 | 1 | Midwest Traffic Signal Services, LLC | MoDOT |
| 20 FEB 2026 | 260220-F02 | St. Louis | 490 | $3.08 | $2.29 | 2 | Raineri Construction, LLC dba Raineri Construction | MoDOT |
| 12 DEC 2025 | 251212-D02 | Central | 170 | $1.50 | $1.50 | 3 | Sam Gaines Construction, Inc. | MoDOT |
| 14 NOV 2025 | 251114-C02 | Kansas City | 610 | $6.85 | $6.85 | 3 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 14 NOV 2025 | 251114-C02 | Kansas City | 320 | $6.85 | $6.85 | 3 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 14 NOV 2025 | 251114-G02 | Southwest | 150 | $2.15 | $2.41 | 3 | D & E Plumbing and Heating, Inc. | MoDOT |
| 17 OCT 2025 | 251017-F05 | St. Louis | 1,230 | $1.05 | $1.05 | 5 | N.B. West Contracting Company | MoDOT |
| 19 SEP 2025 | 250919-F05 | St. Louis | 1,620 | $1.85 | $1.85 | 4 | N.B. West Contracting Company | MoDOT |
| 16 MAY 2025 | 250516-C13 | Kansas City | 740 | $1.90 | $1.90 | 3 | Realm Construction Inc. | MoDOT |
| 16 MAY 2025 | 250516-F01 | St. Louis | 970 | $1.45 | $1.45 | 4 | Gershenson Construction Co., Inc. | MoDOT |
| 16 MAY 2025 | 250516-F09 | St. Louis | 1,630 | $1.30 | $1.52 | 4 | Pace Construction Company, LLC | MoDOT |
| 16 MAY 2025 | 250516-G01 | Southwest | 270 | $1.90 | $1.92 | 6 | Hartman and Company, Inc. | MoDOT |
| 16 MAY 2025 | 250516-G02 | Southwest | 540 | $2.80 | $3.04 | 4 | Hartman and Company, Inc. | MoDOT |
| 21 FEB 2025 | 250221-B07 | Northeast | 450 | $1.40 | $1.90 | 2 | Meyer Electric Company, Inc. | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way