Dynamic pile testing unit price, Missouri

Low bidders on MoDOT contracts carried a median of $4,450.00 per EACH for item 7025001, dynamic pile testing, over the 24 months to 16 OCT 2026, across 36 low bids. Half of all 125 bids fell between $3,700.00 and $5,850.00.

Owner
Missouri DOT
Item
7025001
Unit
EACH
Latest letting
18 JUN 2026
$4,450.00Low bidder's median, per EACH
$4,500.00Median of all bids, per EACH
28Contracts in the window

By year of letting

Dynamic pile testing, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201113$2,448.0065$1,925.00
2021711$3,000.0033$3,000.00
202267$2,400.0019$2,600.00
2023911$3,500.0046$3,500.00
20241722$4,050.0085$4,311.90
20251624$4,500.0080$4,850.00
202688$3,925.0026$4,236.74
Dynamic pile testing, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Dynamic pile testing, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Southeast18$4,825.0069$5,000.00
Northeast7$4,400.0023$4,000.00
Southwest3$3,000.0013$4,473.80
Kansas City4$3,500.008$3,450.00
Dynamic pile testing, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Dynamic pile testing, MoDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
2 to 29$4,500.00
2 to 29$4,500.00
3 to 49$4,500.00
4 to 169$4,400.00
Dynamic pile testing, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Dynamic pile testing
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 JUN 2026260618-H01Southeast2$4,900.00$4,450.004Robertson Contractors, Inc.MoDOT
15 MAY 2026260515-G08Southwest2$3,700.00$4,800.005Hartman and Company, Inc.MoDOT
17 APR 2026260417-D05Central4$4,000.00$5,250.005Joe's Bridge & Grading, Inc.MoDOT
20 MAR 2026260320-B04Northeast2$6,092.95$6,092.951Louis-Company, LLCMoDOT
20 MAR 2026260320-C06Kansas City9$5,845.73$5,001.412Hawkins Construction Company dba Hopco Construction, Inc.MoDOT
16 JAN 2026260116-C02Kansas City2$3,500.00$3,450.002Don Schnieders Excavating Company, Inc.MoDOT
16 JAN 2026260116-G04Southwest2$3,000.00$4,020.005Robertson Contractors, Inc.MoDOT
09 JAN 2026260109-A01Northwest5$3,850.00$4,034.242Clarkson Construction CompanyMoDOT
12 DEC 2025251212-H03Southeast4$4,850.00$4,850.005Robertson Contractors, Inc.MoDOT
12 DEC 2025251212-H04Southeast2$4,500.00$6,140.003Joe's Bridge & Grading, Inc.MoDOT
14 NOV 2025251114-H01Southeast3$4,800.00$4,500.003Joe's Bridge & Grading, Inc.MoDOT
14 NOV 2025251114-H01Southeast4$3,500.00$3,500.003Joe's Bridge & Grading, Inc.MoDOT
14 NOV 2025251114-H01Southeast4$3,500.00$3,500.003Joe's Bridge & Grading, Inc.MoDOT
17 OCT 2025251017-G02Southwest5$2,140.59$5,625.003Emery Sapp & Sons, Inc.MoDOT
17 OCT 2025251017-H01Southeast4$3,500.00$4,510.002Joe's Bridge & Grading, Inc.MoDOT
Latest MoDOT contracts carrying Dynamic pile testing

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy