Nu 35, prestressed concrete nu-girder unit price, Missouri
Low bidders on MoDOT contracts carried a median of $383.00 per LF for item 7056021, nu 35, prestressed concrete nu-girder, over the 24 months to 16 OCT 2026, across 13 low bids. Half of all 51 bids fell between $380.00 and $447.50.
- Owner
- Missouri DOT
- Item
- 7056021
- Unit
- LF
- Latest letting
- 18 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 4 | $291.63 | 20 | $272.50 |
| 2021 | 7 | 7 | $288.80 | 34 | $275.00 |
| 2022 | 4 | 4 | $393.38 | 12 | $398.38 |
| 2023 | 10 | 11 | $430.00 | 45 | $410.00 |
| 2024 | 8 | 8 | $396.50 | 45 | $400.00 |
| 2025 | 6 | 7 | $380.00 | 24 | $413.21 |
| 2026 | 4 | 6 | $383.50 | 27 | $395.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| St. Louis | 5 | $383.00 | 19 | $395.00 |
| Southeast | 3 | $360.00 | 16 | $400.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 182 to 647 | 3 | $360.00 |
| 689 to 876 | 3 | $454.83 |
| 914 to 1,044 | 3 | $380.00 |
| 1,143 to 3,588 | 4 | $383.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 JUN 2026 | 260618-F01 | St. Louis | 1,242 | $386.00 | $402.50 | 4 | Millstone Weber, LLC | MoDOT |
| 18 JUN 2026 | 260618-F01 | St. Louis | 876 | $383.00 | $417.50 | 4 | Millstone Weber, LLC | MoDOT |
| 18 JUN 2026 | 260618-F01 | St. Louis | 1,022 | $384.00 | $411.00 | 4 | Millstone Weber, LLC | MoDOT |
| 15 MAY 2026 | 260515-D05 | Central | 1,387 | $425.00 | $415.00 | 5 | Robertson Contractors, Inc. | MoDOT |
| 15 MAY 2026 | 260515-H03 | Southeast | 647 | $360.00 | $409.50 | 4 | Penzel Construction Company, Inc. | MoDOT |
| 16 JAN 2026 | 260116-H03 | Southeast | 630 | $341.00 | $380.00 | 6 | PCX Construction, LLC | MoDOT |
| 17 OCT 2025 | 251017-F04 | St. Louis | 3,588 | $320.00 | $342.00 | 3 | KCI Construction Company | MoDOT |
| 17 OCT 2025 | 251017-G04 | Southwest | 778 | $507.50 | $461.46 | 2 | Hartman and Company, Inc. | MoDOT |
| 16 MAY 2025 | 250516-F11 | St. Louis | 1,044 | $351.00 | $381.00 | 4 | Gershenson Construction Co., Inc. | MoDOT |
| 14 MAR 2025 | 250314-H02 | Southeast | 182 | $400.00 | $437.50 | 6 | Penzel Construction Company, Inc. | MoDOT |
| 21 FEB 2025 | 250221-B02 | Northeast | 1,143 | $380.00 | $452.50 | 4 | Emery Sapp & Sons, Inc. | MoDOT |
| 21 FEB 2025 | 250221-B02 | Northeast | 914 | $380.00 | $452.50 | 4 | Emery Sapp & Sons, Inc. | MoDOT |
| 17 JAN 2025 | 250117-A01 | Northwest | 689 | $454.83 | $454.83 | 1 | Cale Seymour Construction, LLC | MoDOT |
| 20 SEP 2024 | 240920-H01 | Southeast | 506 | $369.00 | $416.00 | 7 | Joe's Bridge & Grading, Inc. | MoDOT |
| 20 SEP 2024 | 240920-H03 | Southwest | 331 | $395.00 | $442.00 | 3 | Joe's Bridge & Grading, Inc. | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.