Pole foundation (45 ft. or 13.5 m mounting height) unit price, Missouri

Low bidders on MoDOT contracts carried a median of $2,436.00 per EACH for item 9018245, pole foundation (45 ft. or 13.5 m mounting height), over the 24 months to 16 OCT 2026, across 41 low bids. Half of all 138 bids fell between $1,810.25 and $2,800.00.

Owner
Missouri DOT
Item
9018245
Unit
EACH
Latest letting
18 JUN 2026
$2,436.00Low bidder's median, per EACH
$2,269.00Median of all bids, per EACH
38Contracts in the window

By year of letting

Pole foundation (45 ft. or 13.5 m mounting height), MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202011$1,530.002$1,552.95
202133$1,988.0011$1,971.00
20221010$2,004.4925$2,100.00
202398$2,009.2332$2,187.50
20241311$2,020.0051$2,325.00
20252024$2,270.0073$2,035.00
20261111$2,638.0033$2,462.00
Pole foundation (45 ft. or 13.5 m mounting height), MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Pole foundation (45 ft. or 13.5 m mounting height), MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
St. Louis15$2,132.0060$2,035.00
Kansas City7$2,020.0023$2,461.00
Southwest6$2,874.9821$2,919.97
Southeast5$2,340.0015$2,160.18
Central4$2,939.008$2,859.50
Pole foundation (45 ft. or 13.5 m mounting height), MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Pole foundation (45 ft. or 13.5 m mounting height), MoDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 210$2,340.00
2 to 510$2,705.72
5 to 1110$2,352.50
12 to 3711$2,462.00
Pole foundation (45 ft. or 13.5 m mounting height), MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Pole foundation (45 ft. or 13.5 m mounting height)
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 JUN 2026260618-D05Central5$1,250.00$2,149.504Capital Paving & Construction, LLCMoDOT
18 JUN 2026260618-F01St. Louis19$2,462.00$2,462.004Millstone Weber, LLCMoDOT
18 JUN 2026260618-F01St. Louis15$2,462.00$2,462.004Millstone Weber, LLCMoDOT
15 MAY 2026260515-A02Northwest2$3,125.00$3,125.001Leavenworth Excavating & Equipment Company, Inc.MoDOT
15 MAY 2026260515-F01St. Louis1$3,780.00$3,380.003R. V. Wagner, Inc.MoDOT
15 MAY 2026260515-F03St. Louis11$2,269.00$2,269.004N.B. West Contracting CompanyMoDOT
15 MAY 2026260515-G02Southwest4$3,125.00$3,125.001Midwest Traffic Signal Services, LLCMoDOT
17 APR 2026260417-G01Southwest6$3,555.00$3,377.504Radmacher Brothers Excavating Co., Inc.MoDOT
20 MAR 2026260320-D03Central5$2,638.00$2,719.002Don Schnieders Excavating Company, Inc.MoDOT
20 MAR 2026260320-H02Southeast9$2,436.00$2,436.003Lappe Cement Finishing, Inc.MoDOT
20 FEB 2026260220-F02St. Louis4$2,773.44$2,414.722Raineri Construction, LLC dba Raineri ConstructionMoDOT
16 JAN 2026260116-F08St. Louis21n/a$2,000.001MoDOT
12 DEC 2025251212-C02Kansas City1$2,572.43$2,572.431Clarkson Construction CompanyMoDOT
14 NOV 2025251114-C02Kansas City2$1,737.50$1,737.503Radmacher Brothers Excavating Co., Inc.MoDOT
14 NOV 2025251114-C02Kansas City2$1,737.50$1,737.503Radmacher Brothers Excavating Co., Inc.MoDOT
Latest MoDOT contracts carrying Pole foundation (45 ft. or 13.5 m mounting height)

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy