Pull box, preformed class 3 unit price, Missouri
Low bidders on MoDOT contracts carried a median of $3,507.50 per EACH for item 9028812, pull box, preformed class 3, over the 24 months to 16 OCT 2026, across 24 low bids. Half of all 81 bids fell between $3,170.00 and $4,290.00.
- Owner
- Missouri DOT
- Item
- 9028812
- Unit
- EACH
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 6 | $1,890.00 | 15 | $1,604.00 |
| 2021 | 3 | 3 | $1,755.00 | 7 | $1,850.00 |
| 2022 | 10 | 10 | $3,008.00 | 23 | $3,011.00 |
| 2023 | 10 | 11 | $3,475.00 | 35 | $3,500.00 |
| 2024 | 10 | 10 | $3,507.50 | 35 | $3,212.00 |
| 2025 | 14 | 15 | $3,500.00 | 47 | $3,500.00 |
| 2026 | 6 | 6 | $3,932.00 | 20 | $3,919.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| St. Louis | 9 | $3,238.00 | 37 | $3,170.00 |
| Kansas City | 9 | $4,316.58 | 26 | $4,423.50 |
| Central | 4 | $3,457.50 | 13 | $3,400.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 6 | $3,609.07 |
| 1 to 2 | 6 | $3,727.50 |
| 2 to 4 | 6 | $3,724.00 |
| 5 to 16 | 6 | $3,179.06 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 260918-C04 | Kansas City | 5 | $4,435.00 | $3,689.55 | 3 | Amino Bros. Co., Inc. | MoDOT |
| 15 MAY 2026 | 260515-C14 | Kansas City | 2 | $3,864.00 | $3,864.00 | 3 | Realm Construction Inc. | MoDOT |
| 15 MAY 2026 | 260515-F03 | St. Louis | 11 | $3,238.00 | $3,238.00 | 4 | N.B. West Contracting Company | MoDOT |
| 17 APR 2026 | 260417-D03 | Central | 2 | $4,620.00 | $4,530.00 | 2 | Ti-Zack Concrete, LLC | MoDOT |
| 20 FEB 2026 | 260220-C01 | Kansas City | 2 | $4,000.00 | $4,410.70 | 4 | Amino Bros. Co., Inc. | MoDOT |
| 16 JAN 2026 | 260116-D06 | Central | 1 | $1,660.00 | $4,045.00 | 4 | Garrett Power Constructors Corp | MoDOT |
| 12 DEC 2025 | 251212-D02 | Central | 1 | $3,400.00 | $3,400.00 | 3 | Sam Gaines Construction, Inc. | MoDOT |
| 14 NOV 2025 | 251114-C02 | Kansas City | 3 | $4,738.00 | $4,738.00 | 3 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 14 NOV 2025 | 251114-C02 | Kansas City | 1 | $4,738.00 | $4,738.00 | 3 | Radmacher Brothers Excavating Co., Inc. | MoDOT |
| 14 NOV 2025 | 251114-F04 | St. Louis | 4 | $3,584.00 | $3,584.00 | 4 | Gershenson Construction Co., Inc. | MoDOT |
| 14 NOV 2025 | 251114-F05 | St. Louis | 1 | $3,500.00 | $3,500.00 | 4 | N.B. West Contracting Company | MoDOT |
| 17 OCT 2025 | 251017-A04 | Northwest | 2 | $3,940.00 | $3,982.50 | 2 | Clarkson Construction Company | MoDOT |
| 17 OCT 2025 | 251017-F05 | St. Louis | 4 | $3,170.00 | $3,170.00 | 5 | N.B. West Contracting Company | MoDOT |
| 17 OCT 2025 | 251017-G02 | Southwest | 1 | $3,205.39 | $3,070.00 | 3 | Emery Sapp & Sons, Inc. | MoDOT |
| 19 SEP 2025 | 250919-F05 | St. Louis | 8 | $3,020.00 | $3,020.00 | 4 | N.B. West Contracting Company | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way