Replacement sand barrel unit price, Missouri
Low bidders on MoDOT contracts carried a median of $433.12 per EACH for item 6122020, replacement sand barrel, over the 24 months to 16 OCT 2026, across 72 low bids. Half of all 229 bids fell between $303.00 and $525.00.
- Owner
- Missouri DOT
- Item
- 6122020
- Unit
- EACH
- Latest letting
- 18 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 18 | 20 | $310.00 | 89 | $316.50 |
| 2021 | 25 | 26 | $300.00 | 96 | $300.00 |
| 2022 | 25 | 25 | $365.00 | 70 | $400.00 |
| 2023 | 31 | 30 | $411.50 | 91 | $370.00 |
| 2024 | 31 | 33 | $325.00 | 107 | $339.07 |
| 2025 | 35 | 37 | $460.00 | 120 | $460.00 |
| 2026 | 20 | 21 | $400.00 | 66 | $401.51 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| St. Louis | 14 | $537.50 | 55 | $525.00 |
| Kansas City | 18 | $400.00 | 48 | $401.51 |
| Southeast | 11 | $350.00 | 36 | $390.81 |
| Central | 12 | $232.43 | 34 | $233.70 |
| Northwest | 9 | $500.00 | 33 | $500.00 |
| Southwest | 5 | $409.84 | 14 | $400.00 |
| Northeast | 3 | $523.00 | 9 | $475.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 18 | $312.50 |
| 2 to 4 | 18 | $375.00 |
| 4 to 8 | 18 | $410.62 |
| 8 to 130 | 18 | $493.55 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 SEP 2026 | 260918-C04 | Kansas City | 7 | $292.00 | $282.50 | 3 | Amino Bros. Co., Inc. | MoDOT |
| 18 SEP 2026 | 260918-H02 | Southeast | 2 | $345.00 | $898.09 | 2 | West Plains Bridge & Grading, LLC | MoDOT |
| 18 SEP 2026 | 260918-H03 | Southeast | 2 | $345.00 | $899.66 | 2 | West Plains Bridge & Grading, LLC | MoDOT |
| 18 JUN 2026 | 260618-C02 | Kansas City | 5 | $478.66 | $438.00 | 4 | Louis-Company, LLC | MoDOT |
| 18 JUN 2026 | 260618-F01 | St. Louis | 30 | $1,125.00 | $525.00 | 4 | Millstone Weber, LLC | MoDOT |
| 18 JUN 2026 | 260618-F01 | St. Louis | 130 | $1,088.00 | $525.00 | 4 | Millstone Weber, LLC | MoDOT |
| 15 MAY 2026 | 260515-C13 | Kansas City | 4 | $400.00 | $361.70 | 3 | E & C Bridge, LLC | MoDOT |
| 15 MAY 2026 | 260515-D03 | Central | 2 | $490.00 | $490.00 | 4 | H.R. Quadri Contractors, LLC | MoDOT |
| 15 MAY 2026 | 260515-F03 | St. Louis | 10 | $495.10 | $495.00 | 4 | N.B. West Contracting Company | MoDOT |
| 15 MAY 2026 | 260515-G06 | Southwest | 4 | $200.00 | $216.25 | 4 | Hartman and Company, Inc. | MoDOT |
| 17 APR 2026 | 260417-C01 | Kansas City | 4 | $514.29 | $475.00 | 4 | Comanche Construction, Inc. | MoDOT |
| 17 APR 2026 | 260417-C06 | Kansas City | 4 | $334.37 | $334.37 | 3 | Comanche Construction, Inc. | MoDOT |
| 17 APR 2026 | 260417-C09 | Kansas City | 3 | $400.00 | $451.85 | 3 | Leavenworth Excavating & Equipment Company, Inc. | MoDOT |
| 20 MAR 2026 | 260320-B03 | Northeast | 20 | $300.00 | $300.00 | 1 | Magruder Construction Co., Inc. | MoDOT |
| 20 MAR 2026 | 260320-D01 | Central | 6 | $264.76 | $281.38 | 4 | Louis-Company, LLC | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.