Rock ditch check unit price, Missouri

Low bidders on MoDOT contracts carried a median of $16.00 per LF for item 8061005, rock ditch check, over the 24 months to 16 OCT 2026, across 184 low bids. Half of all 649 bids fell between $14.00 and $33.00.

Owner
Missouri DOT
Item
8061005
Unit
LF
Latest letting
16 OCT 2026
$16.00Low bidder's median, per LF
$17.25Median of all bids, per LF
154Contracts in the window

By year of letting

Rock ditch check, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20206879$19.00351$20.00
20216977$15.40292$15.00
20227380$18.36265$20.00
20238188$20.00321$20.50
20247488$17.23352$20.00
202586108$17.25378$20.00
20265054$16.00184$18.39
Rock ditch check, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Rock ditch check, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Southeast42$15.00155$17.28
Southwest34$14.90121$15.80
Central29$15.89107$15.89
St. Louis22$18.0082$20.00
Northeast16$16.0071$15.00
Kansas City27$44.1268$46.00
Northwest14$26.5045$32.15
Rock ditch check, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Rock ditch check, MoDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
6 to 5446$40.00
56 to 14046$16.00
140 to 42546$15.95
432 to 26,97346$13.18
Rock ditch check, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Rock ditch check
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-F06St. Louis14$140.00$45.005Midwest Mechanical and Welding, LLCMoDOT
16 OCT 2026261016-G01Southwest930$13.67$15.003APAC-Central, Inc.MoDOT
16 OCT 2026261016-G01Southwest2,340$13.69$15.003APAC-Central, Inc.MoDOT
16 OCT 2026261016-G01Southwest350$13.71$15.003APAC-Central, Inc.MoDOT
16 OCT 2026261016-G11Southwest640$15.80$15.007Radmacher Brothers Excavating Co., Inc.MoDOT
18 SEP 2026260918-C04Kansas City96$79.85$79.853Amino Bros. Co., Inc.MoDOT
18 SEP 2026260918-D11Central2,457$13.00$13.506TB Dozing & Excavation, LLCMoDOT
18 SEP 2026260918-F05St. Louis98$16.00$16.001Gershenson Construction Co., Inc.MoDOT
18 JUN 2026260618-D05Central198$30.00$30.004Capital Paving & Construction, LLCMoDOT
18 JUN 2026260618-F01St. Louis70$20.00$20.004Millstone Weber, LLCMoDOT
18 JUN 2026260618-H03Southeast300$14.00$19.006Robertson Contractors, Inc.MoDOT
15 MAY 2026260515-C08Kansas City74$14.00$54.694Widel, Inc.MoDOT
15 MAY 2026260515-C14Kansas City6$90.30$112.003Realm Construction Inc.MoDOT
15 MAY 2026260515-D02Central56$25.00$25.003Widel, Inc.MoDOT
15 MAY 2026260515-D02Central48$25.00$25.003Widel, Inc.MoDOT
Latest MoDOT contracts carrying Rock ditch check

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy