Tack coat unit price, Missouri

Low bidders on MoDOT contracts carried a median of $3.00 per GAL for item 4071005, tack coat, over the 24 months to 16 OCT 2026, across 299 low bids. Half of all 911 bids fell between $2.75 and $3.65.

Owner
Missouri DOT
Item
4071005
Unit
GAL
Latest letting
16 OCT 2026
$3.00Low bidder's median, per GAL
$3.00Median of all bids, per GAL
212Contracts in the window

By year of letting

Tack coat, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202093147$2.10474$2.17
2021102163$2.27477$2.30
202287124$3.00330$3.00
2023105198$3.00525$3.00
2024128190$2.92525$3.00
2025116151$3.00500$3.00
20265071$3.25209$3.25
Tack coat, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Tack coat, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Southeast69$3.15198$3.15
Central58$3.09177$3.25
Southwest44$2.70148$3.00
Northwest32$3.67104$3.00
Kansas City38$2.89102$3.00
Northeast34$3.3793$3.00
St. Louis24$2.8589$3.25
Tack coat, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Tack coat, MoDOT: low bidder's median by quantity band
Quantity (GAL)Low bidsLow-bid median
8 to 72674$3.88
729 to 6,20875$3.00
6,532 to 18,60975$3.00
19,078 to 92,28375$2.75
Tack coat, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Tack coat
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-B01Northeast31,631$2.75$3.292Emery Sapp & Sons, Inc.MoDOT
16 OCT 2026261016-B01Northeast10,244$2.75$3.292Emery Sapp & Sons, Inc.MoDOT
16 OCT 2026261016-B03Northeast12,759$3.70$2.984Magruder Paving, LLCMoDOT
16 OCT 2026261016-D03Central9,316$3.00$3.452Capital Paving & Construction, LLCMoDOT
16 OCT 2026261016-D08Central38,137$3.75$3.403Pace Construction Company, LLCMoDOT
16 OCT 2026261016-D13Central46,174$2.65$2.653Emery Sapp & Sons, Inc.MoDOT
16 OCT 2026261016-F01St. Louis2,961.80$3.30$3.303Pace Construction Company, LLCMoDOT
16 OCT 2026261016-F01St. Louis8,100$2.70$2.703Pace Construction Company, LLCMoDOT
16 OCT 2026261016-F06St. Louis9$750.00$10.005Midwest Mechanical and Welding, LLCMoDOT
16 OCT 2026261016-G01Southwest8,580$3.42$3.253APAC-Central, Inc.MoDOT
16 OCT 2026261016-G01Southwest16,186$3.42$3.253APAC-Central, Inc.MoDOT
16 OCT 2026261016-G01Southwest4,682$3.42$3.253APAC-Central, Inc.MoDOT
16 OCT 2026261016-G01Southwest14,006$3.42$3.323APAC-Central, Inc.MoDOT
16 OCT 2026261016-G10Southwest79,439$3.41$2.803APAC-Central, Inc.MoDOT
16 OCT 2026261016-G10Southwest9,598$3.41$2.803APAC-Central, Inc.MoDOT
Latest MoDOT contracts carrying Tack coat

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy