Temporary short-term rumble strips unit price, Missouri
Low bidders on MoDOT contracts carried a median of $1,325.00 per EACH for item 6162004, temporary short-term rumble strips, from 17 JAN 2020 to 17 MAR 2023, across 210 low bids. Half of all 666 bids fell between $766.71 and $2,000.00.
- Owner
- Missouri DOT
- Item
- 6162004
- Unit
- EACH
- Latest letting
- 17 MAR 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 39 | 62 | $831.50 | 231 | $831.50 |
| 2021 | 57 | 76 | $1,255.00 | 230 | $1,250.00 |
| 2022 | 52 | 61 | $1,950.00 | 179 | $1,757.00 |
| 2023 | 9 | 11 | $2,000.00 | 26 | $2,100.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Southwest | 76 | $1,200.00 | 245 | $1,002.12 |
| Central | 52 | $1,200.00 | 184 | $1,200.00 |
| Northwest | 27 | $1,950.00 | 77 | $2,000.00 |
| Southeast | 23 | $1,200.00 | 70 | $1,315.00 |
| Northeast | 16 | $1,755.53 | 41 | $1,950.00 |
| Kansas City | 11 | $1,580.00 | 35 | $1,500.00 |
| St. Louis | 5 | $1,535.00 | 14 | $2,000.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 4 | 52 | $1,000.00 |
| 4 to 4 | 53 | $1,265.00 |
| 4 to 6 | 52 | $1,625.00 |
| 7 to 28 | 53 | $1,500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 17 MAR 2023 | 230317-A02 | Northwest | 4 | $2,200.00 | $2,075.00 | 2 | Vance Brothers, Inc. | MoDOT |
| 17 MAR 2023 | 230317-B03 | Northeast | 4 | $1,200.00 | $4,281.02 | 2 | Emery Sapp & Sons, Inc. | MoDOT |
| 17 MAR 2023 | 230317-H07 | Southeast | 8 | $2,000.00 | $2,015.62 | 2 | J M Scheidle, LLC | MoDOT |
| 17 FEB 2023 | 230217-H04 | Southeast | 2 | $1,400.00 | $1,400.00 | 1 | Robertson Contractors, Inc. | MoDOT |
| 20 JAN 2023 | 230120-A06 | Northwest | 8 | $2,300.00 | $2,100.00 | 4 | Interstate Improvement, Inc. | MoDOT |
| 20 JAN 2023 | 230120-C09 | Kansas City | 2 | $2,000.00 | $1,975.00 | 2 | Clarkson Construction Company | MoDOT |
| 20 JAN 2023 | 230120-G02 | Southwest | 14 | $2,131.00 | $2,315.50 | 2 | Hunter Chase & Associates, Inc. | MoDOT |
| 20 JAN 2023 | 230120-G04 | Southwest | 8 | $1,450.00 | $2,195.00 | 2 | Blevins Asphalt Construction Company, Inc. | MoDOT |
| 20 JAN 2023 | 230120-H01 | Southeast | 4 | $2,000.00 | $2,500.00 | 3 | Pace Construction Company | MoDOT |
| 20 JAN 2023 | 230120-H01 | Southeast | 4 | $2,000.00 | $2,500.00 | 3 | Pace Construction Company | MoDOT |
| 20 JAN 2023 | 230120-H01 | Southeast | 4 | $2,000.00 | $2,500.00 | 3 | Pace Construction Company | MoDOT |
| 16 DEC 2022 | 221216-B02 | Northeast | 8 | $2,800.00 | $2,927.50 | 2 | Magruder Paving, LLC | MoDOT |
| 16 DEC 2022 | 221216-B03 | Northeast | 4 | $3,062.00 | $3,062.00 | 1 | Emery Sapp & Sons, Inc. | MoDOT |
| 16 DEC 2022 | 221216-B03 | Northeast | 4 | $2,200.00 | $2,200.00 | 1 | Emery Sapp & Sons, Inc. | MoDOT |
| 16 DEC 2022 | 221216-C06 | Kansas City | 2 | $1,650.00 | $5,325.00 | 2 | Emery Sapp & Sons, Inc. | MoDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.
How these prices were read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.