Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints) unit price, Missouri

Low bidders on MoDOT contracts carried a median of $6.25 per EACH for item 6131018, tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), over the 24 months to 16 OCT 2026, across 30 low bids. Half of all 111 bids fell between $3.20 and $10.00.

Owner
Missouri DOT
Item
6131018
Unit
EACH
Latest letting
16 OCT 2026
$6.25Low bidder's median, per EACH
$7.00Median of all bids, per EACH
28Contracts in the window

By year of letting

Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202122$6.883$8.75
20221316$5.5037$6.65
20231113$15.0032$10.44
20241618$9.5356$8.65
20251618$3.4564$3.75
202633$12.9015$9.35
Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Kansas City10$3.3337$3.20
St. Louis9$10.0032$10.00
Southeast4$13.9514$9.75
Central3$8.809$8.80
Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), MoDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
7 to 167$9.75
18 to 328$5.12
40 to 1847$8.75
320 to 3,0708$4.50
Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints), MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints)
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-B04Northeast112$8.75$8.755Magruder Paving, LLCMoDOT
15 MAY 2026260515-F03St. Louis20$56.00$31.004N.B. West Contracting CompanyMoDOT
20 MAR 2026260320-H04Southeast1,484$12.90$11.206Iowa Civil Contracting, Inc.MoDOT
14 NOV 2025251114-C01Kansas City30$3.45$3.205Emery Sapp & Sons, Inc.MoDOT
14 NOV 2025251114-C01Kansas City16$3.45$3.205Emery Sapp & Sons, Inc.MoDOT
17 OCT 2025251017-C01Kansas City3,070$2.80$5.766Emery Sapp & Sons, Inc.MoDOT
17 OCT 2025251017-C06Kansas City26$3.75$3.752Ideker, Inc.MoDOT
17 OCT 2025251017-D02Central12$9.75$9.752Capital Paving & Construction, LLCMoDOT
19 SEP 2025250919-A02Northwest26$2.30$2.304Herzog Contracting Corp.MoDOT
15 AUG 2025250815-F03St. Louis320$3.00$5.007Lamke Trenching & Excavating, Inc.MoDOT
20 JUN 2025250620-C03Kansas City7$2.90$2.903Superior Bowen Asphalt Company, LLCMoDOT
18 APR 2025250418-C03Kansas City25$3.20$23.003Realm Construction Inc.MoDOT
18 APR 2025250418-F03St. Louis1,092$2.90$13.452Emery Sapp & Sons, Inc.MoDOT
14 MAR 2025250314-C01Kansas City32$6.50$3.753Emery Sapp & Sons, Inc.MoDOT
14 MAR 2025250314-D06Central392$6.00$6.003Geromini Concrete Paving, LLC dba GC PavingMoDOT
Latest MoDOT contracts carrying Tie bar (drilling, furnishing and installation) for full depth pavement repair (type l joints)

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.