Type A2 shoulder unit price, Missouri

Low bidders on MoDOT contracts carried a median of $65.00 per SY for item 4010150, type a2 shoulder, over the 24 months to 16 OCT 2026, across 31 low bids. Half of all 95 bids fell between $50.00 and $144.50.

Owner
Missouri DOT
Item
4010150
Unit
SY
Latest letting
16 OCT 2026
$65.00Low bidder's median, per SY
$80.00Median of all bids, per SY
29Contracts in the window

By year of letting

Type A2 shoulder, MoDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202089$30.9534$33.47
20211111$43.4033$52.90
20221920$64.5053$78.00
202388$62.3024$62.30
20241516$72.4355$79.30
20251618$53.0550$80.00
202699$71.3031$82.00
Type A2 shoulder, MoDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Type A2 shoulder, MoDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
St. Louis7$70.0025$80.00
Kansas City10$74.2421$135.25
Central5$76.2220$88.50
Southwest5$41.6016$45.20
Southeast3$50.0012$55.00
Type A2 shoulder, MoDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Type A2 shoulder, MoDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
23.20 to 74.407$150.00
75 to 375.808$86.80
409.40 to 1,0078$50.00
1,305.50 to 8,935.608$52.80
Type A2 shoulder, MoDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest MoDOT contracts carrying Type A2 shoulder
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
16 OCT 2026261016-D14Central316.30$76.22$113.006Capital Paving & Construction, LLCMoDOT
16 OCT 2026261016-F01St. Louis55$315.00$230.003Pace Construction Company, LLCMoDOT
15 MAY 2026260515-C13Kansas City253.60$157.35$157.353E & C Bridge, LLCMoDOT
15 MAY 2026260515-G08Southwest1,663.60$71.30$82.005Hartman and Company, Inc.MoDOT
20 MAR 2026260320-C05Kansas City151.40$843.44$506.562Louis-Company, LLCMoDOT
20 MAR 2026260320-D03Central2,598$65.00$85.002Don Schnieders Excavating Company, Inc.MoDOT
20 FEB 2026260220-G01Southwest836.20$42.40$47.202Hartman and Company, Inc.MoDOT
20 FEB 2026260220-G01Southwest2,255.30$29.80$35.902Hartman and Company, Inc.MoDOT
16 JAN 2026260116-F08St. Louis17,575.30n/a$39.001MoDOT
16 JAN 2026260116-H02Southeast633.30$50.00$39.575Robertson Contractors, Inc.MoDOT
14 NOV 2025251114-C04Kansas City69.80$513.43$350.003Ideker, Inc.MoDOT
14 NOV 2025251114-C11Kansas City375.80$97.38$128.482Clarkson Construction CompanyMoDOT
14 NOV 2025251114-F05St. Louis114$70.00$157.004N.B. West Contracting CompanyMoDOT
17 OCT 2025251017-C06Kansas City28.40$358.05$358.052Ideker, Inc.MoDOT
17 OCT 2025251017-D01Central588$38.00$78.314Christensen Construction Co.MoDOT
Latest MoDOT contracts carrying Type A2 shoulder

Filter this item by your own quantity, district and period, or check your price against it, in the MoDOT explorer.

How these prices were read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are MoDOT's own: this item is compared with MoDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.