3" rigid nonmetallic conduit unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $53.50 per LF for item 701030P, 3" rigid nonmetallic conduit, over the 24 months to 16 APR 2026, across 14 low bids. Half of all 57 bids fell between $44.00 and $65.00.

Owner
New Jersey DOT
Item
701030P
Unit
LF
Latest letting
31 MAR 2026
$53.50Low bidder's median, per LF
$54.00Median of all bids, per LF
14Contracts in the window

By year of letting

3" rigid nonmetallic conduit, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201733$21.6014$24.20
20181111$25.0050$25.00
20191313$29.0061$32.00
202044$27.0021$25.00
202177$38.0033$39.00
202266$36.0019$45.00
202399$38.0028$42.66
202477$54.0026$53.00
202555$46.4827$50.94
202622$55.004$70.00
3" rigid nonmetallic conduit, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

3" rigid nonmetallic conduit, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
N15$46.4834$51.97
C13$54.0012$52.00
H44$55.007$60.00
3" rigid nonmetallic conduit, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

3" rigid nonmetallic conduit, NJDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
30 to 1703$45.00
250 to 3944$55.00
420 to 2,5003$54.00
3,126 to 10,5124$45.24
3" rigid nonmetallic conduit, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying 3" rigid nonmetallic conduit
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
31 MAR 202626442H4250$55.00$70.002ORCHARD HOLDINGS, LLCNJDOT
26 MAR 202626441H4250$55.00$77.502ORCHARD HOLDINGS, LLCNJDOT
18 NOV 202525128N13,126$46.48$45.007IEW CONSTRUCTION GROUP, INC.NJDOT
30 OCT 202525130N13,161$20.00$46.504UNION PAVING & CONSTRUCTION CO., INC.NJDOT
12 AUG 202525121N1394$53.00$45.474JOSEPH M. SANZARI, INC.NJDOT
01 MAY 202525102N145$65.00$65.5010SPARWICK CONTRACTING, INC.NJDOT
14 JAN 202524152C1170$45.00$47.502SOUTH STATE, INC.NJDOT
24 OCT 202424148S110,512$44.00$44.003RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
03 OCT 202424130C1253$75.00$72.502BERTO CONSTRUCTION, INC.NJDOT
10 SEP 202424471H42,500$60.00$60.001ORCHARD HOLDINGS, LLCNJDOT
05 SEP 202424470H43,500$55.00$64.502ORCHARD HOLDINGS, LLCNJDOT
27 AUG 202424128S130$44.00$44.001SOUTH STATE, INC.NJDOT
06 JUN 202424119N1420$32.00$41.009SOUTH STATE, INC.NJDOT
04 JUN 202424107C11,540$54.00$52.008C.J. HESSE, INC.NJDOT
02 NOV 202323150S11,379$38.00$38.001SOUTH STATE, INC.NJDOT
Latest NJDOT contracts carrying 3" rigid nonmetallic conduit

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy