9" x 14" concrete vertical curb unit price, New Jersey
Low bidders on NJDOT contracts carried a median of $61.50 per LF for item 607034P, 9" x 14" concrete vertical curb, over the 24 months to 16 APR 2026, across 38 low bids. Half of all 161 bids fell between $48.00 and $100.00.
- Owner
- New Jersey DOT
- Item
- 607034P
- Unit
- LF
- Latest letting
- 19 FEB 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 14 | 14 | $39.00 | 78 | $50.00 |
| 2019 | 23 | 23 | $35.00 | 114 | $44.43 |
| 2020 | 15 | 15 | $40.00 | 87 | $57.38 |
| 2021 | 17 | 16 | $37.00 | 59 | $45.00 |
| 2022 | 21 | 21 | $50.00 | 71 | $53.00 |
| 2023 | 23 | 23 | $50.00 | 75 | $50.00 |
| 2024 | 22 | 22 | $67.50 | 82 | $72.50 |
| 2025 | 18 | 18 | $50.50 | 86 | $55.00 |
| 2026 | 1 | 1 | $75.00 | 4 | $105.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| N1 | 9 | $50.00 | 50 | $58.36 |
| C1 | 9 | $63.00 | 48 | $54.53 |
| S1 | 10 | $64.00 | 28 | $70.00 |
| C4 | 3 | $70.00 | 13 | $85.00 |
| S4 | 3 | $30.00 | 9 | $84.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 33 to 100 | 9 | $100.00 |
| 100 to 200 | 10 | $51.50 |
| 200 to 580 | 9 | $50.00 |
| 647 to 5,674 | 10 | $70.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 19 FEB 2026 | 24474 | H4 | 1,576 | $75.00 | $105.00 | 4 | BERTO CONSTRUCTION, INC. | NJDOT |
| 18 NOV 2025 | 25128 | N1 | 580 | $44.15 | $45.00 | 7 | IEW CONSTRUCTION GROUP, INC. | NJDOT |
| 30 OCT 2025 | 25130 | N1 | 752 | $45.00 | $44.00 | 4 | UNION PAVING & CONSTRUCTION CO., INC. | NJDOT |
| 30 OCT 2025 | 25601 | N1 | 33 | $98.00 | $133.25 | 4 | DAIDONE ELECTRIC, INC. | NJDOT |
| 23 OCT 2025 | 25133 | N1 | 329 | $40.00 | $42.50 | 2 | RITACCO CONSTRUCTION, INC. | NJDOT |
| 23 OCT 2025 | 25136 | S1 | 5,674 | $50.00 | $50.00 | 3 | SOUTH STATE, INC. | NJDOT |
| 16 OCT 2025 | 26447 | S4 | 100 | $30.00 | $84.00 | 3 | M.L. RUBERTON CONSTRUCTION CO., INC. | NJDOT |
| 14 OCT 2025 | 26446 | C4 | 50 | $40.00 | $84.00 | 3 | M.L. RUBERTON CONSTRUCTION CO., INC. | NJDOT |
| 09 OCT 2025 | 26445 | N4 | 100 | $100.00 | $100.00 | 2 | J. FLETCHER CREAMER & SON, INC. | NJDOT |
| 07 OCT 2025 | 25126 | C1 | 133 | $55.00 | $50.00 | 4 | NEW PRINCE CONCRETE CONSTRUCTION CO., INC. | NJDOT |
| 26 AUG 2025 | 25122 | C1 | 334 | $55.00 | $55.00 | 10 | PKF-MARK III, INC. | NJDOT |
| 19 JUN 2025 | 25112 | C1 | 1,069 | $63.00 | $57.58 | 6 | DELLA PELLO PAVING, INC. | NJDOT |
| 05 JUN 2025 | 25111 | S1 | 85 | $70.00 | $77.00 | 3 | SOUTH STATE, INC. | NJDOT |
| 29 MAY 2025 | 25104 | S1 | 174 | $33.50 | $45.00 | 5 | EARLE ASPHALT COMPANY | NJDOT |
| 01 MAY 2025 | 25102 | N1 | 224 | $51.00 | $54.00 | 10 | SPARWICK CONTRACTING, INC. | NJDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.
How these prices were read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.