Controller turn-on unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $10,700 per U for item 702060M, controller turn-on, over the 24 months to 16 APR 2026, across 17 low bids. Half of all 58 bids fell between $8,400.00 and $16,925.

Owner
New Jersey DOT
Item
702060M
Unit
U
Latest letting
27 JAN 2026
$10,700Low bidder's median, per U
$11,375Median of all bids, per U
17Contracts in the window

By year of letting

Controller turn-on, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201766$5,183.0041$5,018.40
20181111$6,194.7758$6,130.00
20191414$6,925.0057$7,075.00
20201717$6,050.00104$6,303.74
20212121$7,260.0089$7,000.00
20221213$12,70539$9,680.00
202399$9,000.0035$9,308.52
20241515$9,369.0051$10,400
202544$13,67514$11,275
202611$24,2004$23,100
Controller turn-on, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Controller turn-on, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
S19$8,000.0024$8,100.00
C15$16,50022$16,600
N13$16,00012$15,000
Controller turn-on, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Controller turn-on, NJDOT: low bidder's median by quantity band
Quantity (U)Low bidsLow-bid median
1 to 14$7,900.00
1 to 24$16,250
2 to 44$9,200.00
5 to 445$9,369.00
Controller turn-on, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Controller turn-on
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
27 JAN 202625129C144$24,200$23,1004EARLE ASPHALT COMPANYNJDOT
07 OCT 202525126C11$20,000$18,2504NEW PRINCE CONCRETE CONSTRUCTION CO., INC.NJDOT
24 JUN 202525117N11$16,000$11,3502BERTO CONSTRUCTION, INC.NJDOT
05 JUN 202525111S15$6,280.00$6,280.003SOUTH STATE, INC.NJDOT
29 MAY 202525104S11$11,350$11,3505EARLE ASPHALT COMPANYNJDOT
10 DEC 202424150S13$10,400$10,4001SOUTH STATE, INC.NJDOT
31 OCT 202424151S14$8,000.00$9,500.002SOUTH STATE, INC.NJDOT
29 OCT 202424146S11$5,000.00$5,500.003SOUTH STATE, INC.NJDOT
24 OCT 202424148S11$5,100.00$5,100.003RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
17 OCT 202424141C11$10,700$14,9404BERTO CONSTRUCTION, INC.NJDOT
03 OCT 202424138S14$4,210.00$4,210.003RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
10 SEP 202424134N12$17,000$15,0006FERREIRA CONSTRUCTION CO., INC.NJDOT
27 AUG 202424128S16$9,325.00$9,325.001SOUTH STATE, INC.NJDOT
04 JUN 202424107C12$16,500$16,6008C.J. HESSE, INC.NJDOT
04 JUN 202424108N18$9,369.00$13,6104SCHIFANO CONSTRUCTION CORP.NJDOT
Latest NJDOT contracts carrying Controller turn-on

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.