Fiber mulching unit price, New Jersey
Low bidders on NJDOT contracts carried a median of $3.00 per SY for item 809006M, fiber mulching, over the 24 months to 16 APR 2026, across 10 low bids. Half of all 41 bids fell between $1.50 and $4.45.
- Owner
- New Jersey DOT
- Item
- 809006M
- Unit
- SY
- Latest letting
- 26 AUG 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2017 | 4 | 4 | $1.00 | 21 | $1.05 |
| 2018 | 9 | 7 | $0.70 | 37 | $1.00 |
| 2019 | 10 | 9 | $1.00 | 53 | $2.00 |
| 2020 | 10 | 10 | $1.00 | 55 | $2.10 |
| 2021 | 10 | 7 | $1.25 | 40 | $1.27 |
| 2022 | 6 | 5 | $3.00 | 17 | $2.70 |
| 2023 | 5 | 5 | $1.65 | 14 | $1.65 |
| 2024 | 8 | 8 | $3.50 | 28 | $3.00 |
| 2025 | 2 | 2 | $1.77 | 13 | $1.71 |
Bid prices as published, not adjusted for inflation.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 AUG 2025 | 25122 | C1 | 12,102 | $0.54 | $1.52 | 10 | PKF-MARK III, INC. | NJDOT |
| 03 APR 2025 | 25103 | S1 | 1,300 | $3.00 | $3.00 | 3 | MIDLANTIC CONSTRUCTION, LLC | NJDOT |
| 10 DEC 2024 | 24150 | S1 | 283 | $13.00 | $13.00 | 1 | SOUTH STATE, INC. | NJDOT |
| 31 OCT 2024 | 24151 | S1 | 1,032 | $3.00 | $2.75 | 2 | SOUTH STATE, INC. | NJDOT |
| 29 OCT 2024 | 24146 | S1 | 720 | $3.00 | $5.00 | 3 | SOUTH STATE, INC. | NJDOT |
| 24 OCT 2024 | 24148 | S1 | 12,089 | $4.45 | $4.25 | 3 | RICHARD E. PIERSON CONSTRUCTION CO., INC. | NJDOT |
| 10 SEP 2024 | 24134 | N1 | 36 | $5.00 | $16.00 | 6 | FERREIRA CONSTRUCTION CO., INC. | NJDOT |
| 06 JUN 2024 | 24120 | S1 | 4,590 | $4.00 | $5.50 | 2 | CREAMER RUBERTON, A JOINT VENTURE | NJDOT |
| 04 JUN 2024 | 24107 | C1 | 72,592 | $1.00 | $1.05 | 8 | C.J. HESSE, INC. | NJDOT |
| 04 JUN 2024 | 24116 | S1 | 37,845 | $1.30 | $1.25 | 3 | SOUTH STATE, INC. | NJDOT |
| 02 NOV 2023 | 23150 | S1 | 21,913 | $1.65 | $1.65 | 1 | SOUTH STATE, INC. | NJDOT |
| 31 OCT 2023 | 23156 | S1 | 54,191 | $1.65 | $1.62 | 4 | EARLE ASPHALT COMPANY | NJDOT |
| 24 AUG 2023 | 23420 | S4 | 60,252 | $1.45 | $1.48 | 2 | ASPEN LANDSCAPING CONTRACTING, INC. | NJDOT |
| 08 JUN 2023 | 23120 | C1 | 751 | $65.00 | $1.00 | 3 | MOUNT CONSTRUCTION CO., INC. | NJDOT |
| 08 JUN 2023 | 23125 | S1 | 6,323 | $2.25 | $2.25 | 4 | SOUTH STATE, INC. | NJDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.
How these prices were read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.