Inlet, type e unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $8,200.00 per U for item 602018M, inlet, type e, over the 24 months to 16 APR 2026, across 15 low bids. Half of all 70 bids fell between $6,227.50 and $9,127.24.

Owner
New Jersey DOT
Item
602018M
Unit
U
Latest letting
18 NOV 2025
$8,200.00Low bidder's median, per U
$7,500.00Median of all bids, per U
15Contracts in the window

By year of letting

Inlet, type e, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201744$3,050.0028$4,057.35
201899$4,325.0044$5,250.00
20191110$4,500.0050$5,362.20
20201010$4,250.0067$5,200.00
20211313$5,300.0075$5,500.00
20221111$7,000.0042$6,850.00
20231818$6,101.0072$6,943.01
20241313$6,825.0054$7,114.12
202577$9,000.0039$7,417.00
Inlet, type e, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Inlet, type e, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
C16$8,700.0033$6,800.00
N14$8,555.0722$8,000.00
S14$7,185.0014$7,900.00
Inlet, type e, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Inlet, type e, NJDOT: low bidder's median by quantity band
Quantity (U)Low bidsLow-bid median
1 to 13$10,000
1 to 44$8,500.00
4 to 174$5,950.00
17 to 634$7,905.07
Inlet, type e, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Inlet, type e
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
18 NOV 202525128N117$9,110.14$9,110.147IEW CONSTRUCTION GROUP, INC.NJDOT
30 OCT 202525130N117$5,800.00$6,700.004UNION PAVING & CONSTRUCTION CO., INC.NJDOT
23 OCT 202525134C11$9,000.00$8,010.005EARLE ASPHALT COMPANYNJDOT
07 OCT 202525126C13$5,000.00$8,050.004NEW PRINCE CONCRETE CONSTRUCTION CO., INC.NJDOT
26 AUG 202525122C122$9,132.94$6,850.0010PKF-MARK III, INC.NJDOT
12 AUG 202525121N11$14,000$7,380.024JOSEPH M. SANZARI, INC.NJDOT
29 MAY 202525104S16$6,100.00$8,500.005EARLE ASPHALT COMPANYNJDOT
07 NOV 202425410H45$550.00$550.001SCHIFANO CONSTRUCTION CORP.NJDOT
29 OCT 202424146S11$8,200.00$8,200.003SOUTH STATE, INC.NJDOT
24 OCT 202424148S163$6,170.00$6,700.003RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
17 OCT 202424141C14$8,400.00$7,050.004BERTO CONSTRUCTION, INC.NJDOT
17 OCT 202424144N13$8,000.00$8,000.007FERREIRA CONSTRUCTION CO., INC.NJDOT
03 OCT 202424130C11$10,000$8,250.002BERTO CONSTRUCTION, INC.NJDOT
04 JUN 202424107C143$6,700.00$6,750.008C.J. HESSE, INC.NJDOT
04 JUN 202424116S14$20,000$7,600.003SOUTH STATE, INC.NJDOT
Latest NJDOT contracts carrying Inlet, type e

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy