Modified thrie beam guide rail unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $65.50 per LF for item 609009M, modified thrie beam guide rail, over the 24 months to 16 APR 2026, across 12 low bids. Half of all 57 bids fell between $57.00 and $150.00.

Owner
New Jersey DOT
Item
609009M
Unit
LF
Latest letting
23 OCT 2025
$65.50Low bidder's median, per LF
$70.00Median of all bids, per LF
12Contracts in the window

By year of letting

Modified thrie beam guide rail, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201733$73.2524$68.50
201877$65.0030$72.00
201977$60.0022$96.00
202077$52.2724$55.00
202166$57.5022$72.50
202266$69.7516$90.00
202399$68.0028$68.50
202466$62.5022$58.60
202577$69.0042$76.25
Modified thrie beam guide rail, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By quantity

Modified thrie beam guide rail, NJDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
25 to 383$220.00
75 to 1,0003$56.00
1,250 to 2,7503$50.00
2,950 to 4,8413$62.00
Modified thrie beam guide rail, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Modified thrie beam guide rail
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
23 OCT 202525136S175$90.00$65.003SOUTH STATE, INC.NJDOT
16 OCT 202526447S41,250$50.00$52.003M.L. RUBERTON CONSTRUCTION CO., INC.NJDOT
14 OCT 202526446C41,000$44.00$49.003M.L. RUBERTON CONSTRUCTION CO., INC.NJDOT
09 OCT 202526445N42,950$69.00$72.002J. FLETCHER CREAMER & SON, INC.NJDOT
26 AUG 202525122C14,841$62.00$61.0010PKF-MARK III, INC.NJDOT
01 MAY 202525102N125$120.00$133.4410SPARWICK CONTRACTING, INC.NJDOT
28 JAN 202524153C138$230.00$230.0011SPARWICK CONTRACTING, INC.NJDOT
24 OCT 202424133N125$220.00$260.004UNION PAVING & CONSTRUCTION CO., INC.NJDOT
22 OCT 202425447S41,250$44.00$44.003M.L. RUBERTON CONSTRUCTION CO., INC.NJDOT
17 OCT 202425446C44,000$25.00$44.003SOUTH STATE, INC.NJDOT
10 OCT 202425445N42,750$69.00$69.003ROAD SAFETY SYSTEMS, LLCNJDOT
06 JUN 202424120S1502$56.00$60.502CREAMER RUBERTON, A JOINT VENTURENJDOT
11 APR 202424103N1580$100.00$57.207UNION PAVING & CONSTRUCTION CO., INC.NJDOT
21 NOV 202324447S41,250$48.00$48.003M.L. RUBERTON CONSTRUCTION CO., INC.NJDOT
16 NOV 202324446C44,000$50.00$50.003SOUTH STATE, INC.NJDOT
Latest NJDOT contracts carrying Modified thrie beam guide rail

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy