Push button installation unit price, New Jersey
Low bidders on NJDOT contracts carried a median of $2,677.50 per U for item 702038M, push button installation, over the 24 months to 16 APR 2026, across 10 low bids. Half of all 36 bids fell between $1,893.75 and $2,787.50.
- Owner
- New Jersey DOT
- Item
- 702038M
- Unit
- U
- Latest letting
- 27 JAN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2017 | 4 | 4 | $1,637.50 | 23 | $1,675.00 |
| 2018 | 8 | 8 | $1,795.00 | 46 | $1,587.95 |
| 2019 | 5 | 5 | $1,750.00 | 26 | $2,000.00 |
| 2020 | 13 | 13 | $1,800.00 | 71 | $1,800.00 |
| 2021 | 15 | 15 | $1,700.00 | 66 | $1,900.00 |
| 2022 | 6 | 6 | $2,175.00 | 17 | $2,500.00 |
| 2023 | 4 | 4 | $1,885.00 | 22 | $1,870.00 |
| 2024 | 7 | 7 | $2,730.00 | 26 | $2,225.00 |
| 2025 | 2 | 2 | $2,650.00 | 6 | $2,800.00 |
| 2026 | 1 | 1 | $1,980.00 | 4 | $2,240.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| C1 | 3 | $1,980.00 | 16 | $1,927.50 |
| S1 | 6 | $2,677.50 | 14 | $2,662.50 |
Districts with at least three low bids, over the last 24 months.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 27 JAN 2026 | 25129 | C1 | 72 | $1,980.00 | $2,240.00 | 4 | EARLE ASPHALT COMPANY | NJDOT |
| 23 OCT 2025 | 25136 | S1 | 2 | $2,900.00 | $3,187.25 | 3 | SOUTH STATE, INC. | NJDOT |
| 05 JUN 2025 | 25111 | S1 | 7 | $2,400.00 | $2,400.00 | 3 | SOUTH STATE, INC. | NJDOT |
| 10 DEC 2024 | 24150 | S1 | 2 | $5,200.00 | $5,200.00 | 1 | SOUTH STATE, INC. | NJDOT |
| 24 OCT 2024 | 24148 | S1 | 2 | $2,730.00 | $2,730.00 | 3 | RICHARD E. PIERSON CONSTRUCTION CO., INC. | NJDOT |
| 17 OCT 2024 | 24141 | C1 | 3 | $3,500.00 | $2,160.00 | 4 | BERTO CONSTRUCTION, INC. | NJDOT |
| 10 SEP 2024 | 24134 | N1 | 2 | $3,000.00 | $2,225.00 | 6 | FERREIRA CONSTRUCTION CO., INC. | NJDOT |
| 27 AUG 2024 | 24128 | S1 | 13 | $2,625.00 | $2,625.00 | 1 | SOUTH STATE, INC. | NJDOT |
| 04 JUN 2024 | 24107 | C1 | 2 | $1,770.00 | $1,760.00 | 8 | C.J. HESSE, INC. | NJDOT |
| 04 JUN 2024 | 24116 | S1 | 5 | $2,150.00 | $2,150.00 | 3 | SOUTH STATE, INC. | NJDOT |
| 31 OCT 2023 | 23156 | S1 | 7 | $2,000.00 | $2,062.50 | 4 | EARLE ASPHALT COMPANY | NJDOT |
| 13 JUN 2023 | 23122 | N1 | 3 | $1,840.00 | $1,840.00 | 7 | CRISDEL GROUP, INC. | NJDOT |
| 09 MAY 2023 | 23114 | C1 | 8 | $1,565.00 | $1,758.28 | 5 | DELLA PELLO PAVING, INC. | NJDOT |
| 04 APR 2023 | 22153 | N1 | 5 | $1,930.00 | $1,715.00 | 6 | DELLA PELLO PAVING, INC. | NJDOT |
| 06 OCT 2022 | 22139 | S1 | 1 | $2,800.00 | $2,800.00 | 3 | SOUTH STATE, INC. | NJDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.
How these prices were read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.