Push button installation unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $2,677.50 per U for item 702038M, push button installation, over the 24 months to 16 APR 2026, across 10 low bids. Half of all 36 bids fell between $1,893.75 and $2,787.50.

Owner
New Jersey DOT
Item
702038M
Unit
U
Latest letting
27 JAN 2026
$2,677.50Low bidder's median, per U
$2,400.00Median of all bids, per U
10Contracts in the window

By year of letting

Push button installation, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201744$1,637.5023$1,675.00
201888$1,795.0046$1,587.95
201955$1,750.0026$2,000.00
20201313$1,800.0071$1,800.00
20211515$1,700.0066$1,900.00
202266$2,175.0017$2,500.00
202344$1,885.0022$1,870.00
202477$2,730.0026$2,225.00
202522$2,650.006$2,800.00
202611$1,980.004$2,240.00
Push button installation, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Push button installation, NJDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
C13$1,980.0016$1,927.50
S16$2,677.5014$2,662.50
Push button installation, NJDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

Latest contracts with this item

Latest NJDOT contracts carrying Push button installation
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
27 JAN 202625129C172$1,980.00$2,240.004EARLE ASPHALT COMPANYNJDOT
23 OCT 202525136S12$2,900.00$3,187.253SOUTH STATE, INC.NJDOT
05 JUN 202525111S17$2,400.00$2,400.003SOUTH STATE, INC.NJDOT
10 DEC 202424150S12$5,200.00$5,200.001SOUTH STATE, INC.NJDOT
24 OCT 202424148S12$2,730.00$2,730.003RICHARD E. PIERSON CONSTRUCTION CO., INC.NJDOT
17 OCT 202424141C13$3,500.00$2,160.004BERTO CONSTRUCTION, INC.NJDOT
10 SEP 202424134N12$3,000.00$2,225.006FERREIRA CONSTRUCTION CO., INC.NJDOT
27 AUG 202424128S113$2,625.00$2,625.001SOUTH STATE, INC.NJDOT
04 JUN 202424107C12$1,770.00$1,760.008C.J. HESSE, INC.NJDOT
04 JUN 202424116S15$2,150.00$2,150.003SOUTH STATE, INC.NJDOT
31 OCT 202323156S17$2,000.00$2,062.504EARLE ASPHALT COMPANYNJDOT
13 JUN 202323122N13$1,840.00$1,840.007CRISDEL GROUP, INC.NJDOT
09 MAY 202323114C18$1,565.00$1,758.285DELLA PELLO PAVING, INC.NJDOT
04 APR 202322153N15$1,930.00$1,715.006DELLA PELLO PAVING, INC.NJDOT
06 OCT 202222139S11$2,800.00$2,800.003SOUTH STATE, INC.NJDOT
Latest NJDOT contracts carrying Push button installation

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy