Reinforced elastomeric bearing assembly unit price, New Jersey
Low bidders on NJDOT contracts carried a median of $6,400.00 per U for item 506006P, reinforced elastomeric bearing assembly, over the 24 months to 16 APR 2026, across 11 low bids. Half of all 60 bids fell between $4,825.00 and $9,275.00.
- Owner
- New Jersey DOT
- Item
- 506006P
- Unit
- U
- Latest letting
- 18 NOV 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2017 | 6 | 9 | $2,500.00 | 74 | $3,040.87 |
| 2018 | 7 | 8 | $2,536.56 | 36 | $2,287.50 |
| 2019 | 7 | 14 | $4,600.00 | 70 | $3,200.00 |
| 2020 | 2 | 2 | $2,186.38 | 19 | $3,016.91 |
| 2021 | 7 | 8 | $3,650.00 | 42 | $4,000.00 |
| 2022 | 5 | 5 | $5,000.00 | 21 | $5,000.00 |
| 2023 | 4 | 4 | $5,300.00 | 17 | $5,700.00 |
| 2024 | 5 | 5 | $2,300.00 | 18 | $4,050.00 |
| 2025 | 7 | 7 | $7,500.00 | 45 | $7,500.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| N1 | 5 | $7,500.00 | 29 | $7,500.00 |
| S1 | 4 | $2,900.00 | 12 | $4,050.00 |
Districts with at least three low bids, over the last 24 months.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 NOV 2025 | 25128 | N1 | 60 | $11,245 | $12,000 | 7 | IEW CONSTRUCTION GROUP, INC. | NJDOT |
| 23 OCT 2025 | 25133 | N1 | 32 | $7,500.00 | $9,750.00 | 2 | RITACCO CONSTRUCTION, INC. | NJDOT |
| 12 AUG 2025 | 25121 | N1 | 24 | $6,400.00 | $6,450.00 | 4 | JOSEPH M. SANZARI, INC. | NJDOT |
| 29 MAY 2025 | 25108 | C1 | 24 | $7,500.00 | $4,775.00 | 8 | RITACCO CONSTRUCTION, INC. | NJDOT |
| 01 MAY 2025 | 25102 | N1 | 36 | $3,500.00 | $4,950.00 | 10 | SPARWICK CONTRACTING, INC. | NJDOT |
| 03 APR 2025 | 25103 | S1 | 22 | $5,600.00 | $5,600.00 | 3 | MIDLANTIC CONSTRUCTION, LLC | NJDOT |
| 28 JAN 2025 | 24153 | C1 | 14 | $11,350 | $9,200.00 | 11 | SPARWICK CONTRACTING, INC. | NJDOT |
| 29 OCT 2024 | 24146 | S1 | 33 | $2,000.00 | $4,100.00 | 3 | SOUTH STATE, INC. | NJDOT |
| 26 SEP 2024 | 24132 | S1 | 24 | $3,800.00 | $3,900.00 | 4 | RICHARD E. PIERSON CONSTRUCTION CO., INC. | NJDOT |
| 10 SEP 2024 | 24134 | N1 | 24 | $12,000 | $8,500.00 | 6 | FERREIRA CONSTRUCTION CO., INC. | NJDOT |
| 06 JUN 2024 | 24122 | S1 | 44 | $1,000.00 | $976.75 | 2 | SOUTH STATE, INC. | NJDOT |
| 04 APR 2024 | 24101 | N1 | 18 | $2,300.00 | $1,600.00 | 3 | J.F.CREAMER & SON A JOINT VENTURE WITH JOSEPH M. SANZARI,INC | NJDOT |
| 12 OCT 2023 | 23132 | N1 | 10 | $3,500.00 | $2,084.74 | 5 | RITACCO CONSTRUCTION, INC. | NJDOT |
| 08 JUN 2023 | 23120 | C1 | 24 | $5,500.00 | $5,500.00 | 3 | MOUNT CONSTRUCTION CO., INC. | NJDOT |
| 08 JUN 2023 | 23125 | S1 | 40 | $5,100.00 | $5,700.00 | 4 | SOUTH STATE, INC. | NJDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.
How these prices were read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way