Removal and replacement of rpm lens unit price, New Jersey
Low bidders on NJDOT contracts carried a median of $17.00 per U for item 610027M, removal and replacement of rpm lens, over the 24 months to 16 APR 2026, across 11 low bids. Half of all 30 bids fell between $17.00 and $23.75.
- Owner
- New Jersey DOT
- Item
- 610027M
- Unit
- U
- Latest letting
- 22 JAN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2017 | 1 | 1 | $20.00 | 3 | $20.00 |
| 2018 | 14 | 14 | $14.70 | 28 | $15.24 |
| 2019 | 2 | 2 | $23.51 | 5 | $25.00 |
| 2020 | 8 | 8 | $15.80 | 28 | $20.00 |
| 2021 | 8 | 8 | $16.60 | 18 | $17.00 |
| 2022 | 2 | 2 | $60.97 | 5 | $28.69 |
| 2023 | 10 | 10 | $17.23 | 27 | $18.00 |
| 2025 | 7 | 7 | $16.00 | 20 | $18.25 |
| 2026 | 4 | 4 | $17.50 | 10 | $18.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| S4 | 4 | $15.18 | 11 | $18.25 |
| C4 | 3 | $16.00 | 10 | $18.00 |
| N4 | 3 | $18.00 | 7 | $19.55 |
Districts with at least three low bids, over the last 24 months.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JAN 2026 | 26413 | S4 | 47,600 | $7.00 | $15.50 | 3 | ZONE STRIPING, INC. | NJDOT |
| 15 JAN 2026 | 26412 | C4 | 60,000 | $17.00 | $18.00 | 3 | TRAFFIC LINES, INC. | NJDOT |
| 13 JAN 2026 | 26411 | N4 | 53,000 | $18.00 | $19.00 | 2 | DENVILLE LINE PAINTING, INC. | NJDOT |
| 08 JAN 2026 | 25472 | S4 | 250 | $25.00 | $27.50 | 2 | ZONE STRIPING, INC. | NJDOT |
| 25 NOV 2025 | 25603 | S1 | 110 | $31.00 | $48.00 | 2 | ORCHARD HOLDINGS, LLC | NJDOT |
| 11 FEB 2025 | 25450 | S4 | 250 | $14.85 | $15.00 | 3 | DAN SWAYZE & SON, INC. | NJDOT |
| 04 FEB 2025 | 25449 | C4 | 250 | $15.00 | $22.50 | 4 | DAN SWAYZE & SON, INC. | NJDOT |
| 30 JAN 2025 | 25448 | N4 | 250 | $20.00 | $22.50 | 2 | DENVILLE LINE PAINTING, INC. | NJDOT |
| 23 JAN 2025 | 25462 | S4 | 65,000 | $15.50 | $18.25 | 3 | ZONE STRIPING, INC. | NJDOT |
| 16 JAN 2025 | 25461 | C4 | 77,000 | $16.00 | $17.00 | 3 | TRAFFIC LINES, INC. | NJDOT |
| 14 JAN 2025 | 25460 | N4 | 68,000 | $18.00 | $18.00 | 3 | DENVILLE LINE PAINTING, INC. | NJDOT |
| 19 DEC 2023 | 24413 | S4 | 60,000 | $16.90 | $16.95 | 2 | ZONE STRIPING, INC. | NJDOT |
| 14 DEC 2023 | 24412 | C4 | 81,500 | $15.00 | $15.00 | 3 | TRAFFIC LINES, INC. | NJDOT |
| 07 DEC 2023 | 24411 | N4 | 82,900 | $18.00 | $17.50 | 2 | DENVILLE LINE PAINTING, INC. | NJDOT |
| 31 OCT 2023 | 23157 | N1 | 55 | $30.00 | $30.00 | 5 | RENCOR, INC. | NJDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.
How these prices were read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.