Riprap stone slope protection unit price, New Jersey

Low bidders on NJDOT contracts carried a median of $60.75 per T for item MMG036M, riprap stone slope protection, over the 24 months to 16 APR 2026, across 4 low bids. Half of all 30 bids fell between $54.56 and $157.00.

Owner
New Jersey DOT
Item
MMG036M
Unit
T
Latest letting
19 FEB 2026
$60.75Low bidder's median, per T
$107.50Median of all bids, per T
9Contracts in the window

By year of letting

Riprap stone slope protection, NJDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201843$25.0022$39.00
201932$18.0014$72.50
202066$22.5032$90.00
202176$12.5031$40.00
202262$22.5011$35.00
202332$80.0010$100.00
202463$100.0017$93.60
202551$5.0011$150.00
202622$60.7517$115.00
Riprap stone slope protection, NJDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Riprap stone slope protection, NJDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
N410$33.0067$90.00
C48$10.0051$50.00
H46$35.0016$37.50
Riprap stone slope protection, NJDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Riprap stone slope protection, NJDOT: low bidder's median by quantity band
Quantity (T)Low bidsLow-bid median
25 to 506$10.00
50 to 1007$10.00
100 to 1007$35.00
100 to 2,4127$71.50
Riprap stone slope protection, NJDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NJDOT contracts carrying Riprap stone slope protection
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
19 FEB 202626402N1150$50.00$100.009DELLA PELLO PAVING, INC.NJDOT
13 JAN 202626401N4364$71.50$132.506DELLA PELLO PAVING, INC.NJDOT
13 JAN 202626401N450n/a$120.092DELLA PELLO PAVING, INC.NJDOT
09 DEC 202526403C450n/a$150.003KYLE CONTI CONSTRUCTION, LLCNJDOT
24 APR 202525402N450n/a$10.001SCHIFANO CONSTRUCTION CORP.NJDOT
10 APR 202525403N450n/a$150.003SCHIFANO CONSTRUCTION CORP.NJDOT
20 MAR 202525405C450$5.00$99.312DELLA PELLO PAVING, INC.NJDOT
27 FEB 202525404C450n/a$113.472EARLE ASPHALT COMPANYNJDOT
07 NOV 202425410H4100$100.00$100.001SCHIFANO CONSTRUCTION CORP.NJDOT
16 MAY 202424405C450n/a$75.001SCHIFANO CONSTRUCTION CORP.NJDOT
11 APR 202424402N450n/a$70.003SCHIFANO CONSTRUCTION CORP.NJDOT
09 APR 202424401N4148$135.00$95.004DELLA PELLO PAVING, INC.NJDOT
09 APR 202424401N450n/a$122.502DELLA PELLO PAVING, INC.NJDOT
09 APR 202424406S12,412$40.00$63.003EARLE ASPHALT COMPANYNJDOT
09 APR 202424406S150n/a$135.252EARLE ASPHALT COMPANYNJDOT
Latest NJDOT contracts carrying Riprap stone slope protection

Filter this item by your own quantity, district and period, or check your price against it, in the NJDOT explorer.

How these prices were read

NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NJDOT's own: this item is compared with NJDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy