3'-0" x 2'-0"prestr slabs unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $311.50 per LF for item 8763000000-E, 3'-0" x 2'-0"prestr slabs, over the 24 months to 20 OCT 2026, across 2 low bids. Half of all 9 bids fell between $300.00 and $327.00.
- Owner
- North Carolina DOT
- Item
- 8763000000-E
- Unit
- LF
- Latest letting
- 18 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 27 | 27 | $145.90 | 138 | $155.00 |
| 2014 | 9 | 9 | $165.00 | 46 | $161.00 |
| 2015 | 4 | 4 | $158.44 | 37 | $160.00 |
| 2016 | 9 | 9 | $170.00 | 46 | $175.00 |
| 2017 | 4 | 4 | $156.00 | 30 | $175.00 |
| 2018 | 9 | 9 | $166.56 | 55 | $180.00 |
| 2020 | 4 | 4 | $183.18 | 36 | $171.50 |
| 2021 | 10 | 10 | $187.33 | 67 | $196.95 |
| 2022 | 4 | 4 | $274.55 | 23 | $280.00 |
| 2023 | 2 | 2 | $273.67 | 11 | $256.00 |
| 2024 | 3 | 3 | $230.00 | 22 | $232.00 |
| 2026 | 2 | 2 | $311.50 | 9 | $308.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Wilkes | 6 | $174.48 | 40 | $176.88 |
| Sampson | 3 | $145.00 | 31 | $168.05 |
| Alamance | 3 | $165.00 | 30 | $158.50 |
| Granville | 3 | $145.00 | 21 | $156.00 |
| Transylvania | 5 | $200.00 | 21 | $197.10 |
| Johnston | 3 | $160.00 | 19 | $160.00 |
| Henderson | 3 | $153.00 | 19 | $153.00 |
| Brunswick | 3 | $230.00 | 18 | $238.67 |
| Guilford | 3 | $145.35 | 18 | $162.50 |
| Wake | 3 | $145.00 | 16 | $215.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 436.81 to 700 | 21 | $175.00 |
| 700 to 780 | 22 | $159.00 |
| 825 to 1,265 | 22 | $171.00 |
| 1,300 to 8,625 | 22 | $152.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 AUG 2026 | C204877 | Rutherford | 1,870 | $315.00 | $310.90 | 8 | R E BURNS & SONS CO INC | NCDOT |
| 16 JUN 2026 | C204742 | Pamlico | 4,550 | $308.00 | $308.00 | 1 | SANFORD CONTRACTORS INC | NCDOT |
| 17 SEP 2024 | C204914 | Brunswick | 4,620 | $230.00 | $230.00 | 9 | S&C CONSTRUCTION LLC | NCDOT |
| 28 MAY 2024 | C204411 | Haywood | 825 | $315.00 | $537.50 | 4 | WHALEY CONSTRUCTION, LLC. | NCDOT |
| 16 JAN 2024 | C204830 | Stanly | 2,970 | $197.73 | $225.00 | 9 | SMITH-ROWE, LLC | NCDOT |
| 18 JUL 2023 | C204715 | Jackson | 1,120 | $310.00 | $268.91 | 6 | IPC PAVING LLC DBA IPC STRUCTURES LLC | NCDOT |
| 16 MAY 2023 | C204853 | Brunswick | 8,625 | $237.34 | $240.00 | 5 | S & C CONSTRUCTION LLC | NCDOT |
| 20 DEC 2022 | C204435 | Pender | 1,050 | $269.10 | $287.50 | 6 | S & C CONSTRUCTION LLC | NCDOT |
| 18 OCT 2022 | C204207 | Wake | 1,190 | $280.00 | $285.00 | 6 | CATON CONSTRUCTION GROUP INC | NCDOT |
| 19 JUL 2022 | C204538 | Yadkin | 600 | $230.00 | $249.80 | 7 | EASTERN STRUCTURES LLC | NCDOT |
| 19 APR 2022 | C204484 | Madison | 840 | $400.00 | $425.00 | 4 | DELLINGER INC | NCDOT |
| 21 DEC 2021 | C204623 | Brunswick | 980 | $194.00 | $223.88 | 4 | THE TARA GROUP OF LUMBERTON INC | NCDOT |
| 20 JUL 2021 | C204550 | Wilkes | 700 | $177.41 | $230.87 | 5 | SMITH-ROWE, LLC | NCDOT |
| 20 JUL 2021 | C204628 | Wilkes | 700 | $180.66 | $237.80 | 5 | SMITH-ROWE, LLC | NCDOT |
| 20 JUL 2021 | C204627 | Iredell | 650 | $173.82 | $204.47 | 8 | SMITH-ROWE, LLC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.