4" concrete paved ditch unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $166.65 per SY for item 2619000000-E, 4" concrete paved ditch, over the 24 months to 20 OCT 2026, across 29 low bids. Half of all 173 bids fell between $122.00 and $216.00.
- Owner
- North Carolina DOT
- Item
- 2619000000-E
- Unit
- SY
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 16 | 16 | $50.00 | 84 | $55.00 |
| 2014 | 13 | 13 | $56.00 | 94 | $60.00 |
| 2015 | 14 | 14 | $69.19 | 99 | $65.00 |
| 2016 | 6 | 6 | $65.31 | 37 | $61.00 |
| 2017 | 8 | 8 | $67.00 | 63 | $72.45 |
| 2018 | 16 | 16 | $93.63 | 74 | $93.63 |
| 2019 | 14 | 14 | $89.12 | 61 | $90.00 |
| 2020 | 2 | 2 | $96.50 | 7 | $100.00 |
| 2021 | 17 | 17 | $100.00 | 70 | $110.00 |
| 2022 | 14 | 14 | $173.55 | 49 | $150.00 |
| 2023 | 18 | 18 | $172.75 | 84 | $165.25 |
| 2024 | 13 | 13 | $175.00 | 63 | $175.00 |
| 2025 | 13 | 13 | $152.95 | 85 | $166.65 |
| 2026 | 16 | 16 | $194.00 | 88 | $170.57 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 4.50 to 40 | 7 | $215.00 |
| 40 to 70 | 7 | $210.00 |
| 70 to 120 | 7 | $152.95 |
| 130 to 1,195 | 8 | $115.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C204338 | Wake | 410 | $85.00 | $97.00 | 8 | BLYTHE CONSTRUCTION INC | NCDOT |
| 15 SEP 2026 | C205203 | Wayne | 60 | $60.00 | $74.00 | 6 | LEGION ASPHALT INC | NCDOT |
| 15 SEP 2026 | C204947 | Caldwell | 215 | $178.00 | $156.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 AUG 2026 | C205195 | Catawba | 42 | $210.00 | $183.50 | 4 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 700 | $121.00 | $121.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 21 JUL 2026 | C205225 | Polk | 70 | $300.00 | $253.00 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 16 JUN 2026 | C205186 | Rockingham | 70 | $166.15 | $175.57 | 6 | W C ENGLISH INCORPORATED | NCDOT |
| 16 JUN 2026 | C205157 | Randolph | 72 | $128.50 | $195.00 | 11 | BRANCH CIVIL INC | NCDOT |
| 19 MAY 2026 | C205187 | Cumberland | 90 | $250.00 | $362.00 | 4 | HIGHLAND PAVING CO LLC | NCDOT |
| 19 MAY 2026 | C204733 | Yadkin | 120 | $107.97 | $203.50 | 4 | BLYTHE CONSTRUCTION INC | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 15 | $216.73 | $215.87 | 10 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 19 MAY 2026 | C205159 | Graham | 145 | $250.00 | $242.00 | 3 | WATSON CONTRACTING INC | NCDOT |
| 21 APR 2026 | C204857 | Johnston | 20 | $216.00 | $216.00 | 7 | SUNROCK INDUSTRIES LLC DBA CAROLINA SUNROCK LLC | NCDOT |
| 21 APR 2026 | C205180 | Henderson | 1,195 | $100.00 | $142.37 | 2 | MOUNTAIN CREEK CONTRACTORS INC | NCDOT |
| 24 MAR 2026 | C205165 | Polk | 70 | $220.92 | $194.78 | 5 | SITE DEVELOPMENT CORPORATION | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.