4" slope protection unit price, North Carolina

Low bidders on NCDOT contracts carried a median of $207.00 per SY for item 8531000000-E, 4" slope protection, over the 24 months to 20 OCT 2026, across 23 low bids. Half of all 139 bids fell between $144.50 and $284.84.

Owner
North Carolina DOT
Item
8531000000-E
Unit
SY
Latest letting
20 OCT 2026
$207.00Low bidder's median, per SY
$193.36Median of all bids, per SY
23Contracts in the window

By year of letting

4" slope protection, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20131919$70.00116$74.42
20141414$67.2897$70.10
20151515$85.0093$90.00
201689$86.1049$100.00
20171010$117.0960$98.19
20181111$85.0061$93.00
201999$120.0049$115.00
20211515$100.0073$126.00
20221414$129.8464$150.00
20231515$150.0080$165.50
20241110$187.5068$165.00
20251212$192.2479$190.00
20261010$221.0151$207.00
4" slope protection, NCDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

4" slope protection, NCDOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Rockingham5$407.8023$250.00
Forsyth4$217.0821$207.00
4" slope protection, NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

4" slope protection, NCDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
10 to 30.805$370.13
46 to 546$321.42
56 to 476.206$171.24
522 to 5,0336$132.50
4" slope protection, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NCDOT contracts carrying 4" slope protection
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C204338Wake2,230$57.31$108.958BLYTHE CONSTRUCTION INCNCDOT
18 AUG 2026C205205Robeson522$130.00$142.502BMCO CONSTRUCTION INCNCDOT
18 AUG 2026C204504Watauga30.80$336.00$336.003BRANCH CIVIL INCNCDOT
18 AUG 2026C205070Rutherford12$350.00$791.249UNITED INFRASTRUCTURE GROUP INCNCDOT
16 JUN 2026C205160Forsyth56$207.00$207.005BLYTHE CONSTRUCTION INCNCDOT
16 JUN 2026C205186Rockingham54$195.00$207.506W C ENGLISH INCORPORATEDNCDOT
19 MAY 2026C205187Cumberland52$434.49$442.254HIGHLAND PAVING CO LLCNCDOT
19 MAY 2026C204733Yadkin46$235.03$205.014BLYTHE CONSTRUCTION INCNCDOT
20 JAN 2026C204814Wayne326$80.00$115.007BLYTHE CONSTRUCTION INCNCDOT
20 JAN 2026C205128Rockingham20.20$789.18$400.003SMITH-ROWE, LLCNCDOT
16 DEC 2025C205018Rockingham54$407.80$225.006SMITH-ROWE, LLCNCDOT
18 NOV 2025C205012Forsyth53.60$440.00$250.005APAC ATLANTIC INC SMITH ROWE LLC JVNCDOT
21 OCT 2025C205116Rockingham22$370.13$282.564SMITH-ROWE, LLCNCDOT
21 OCT 2025C205093Davie580$186.00$178.0010BRANCH CIVIL INCNCDOT
19 AUG 2025C204829Rockingham10$500.00$444.884BLYTHE CONSTRUCTION INCNCDOT
Latest NCDOT contracts carrying 4" slope protection

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy