54" rc pipe culv iii unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $445.00 per LF for item 0408000000-E, 54" rc pipe culv iii, over the 24 months to 20 OCT 2026, across 5 low bids. Half of all 25 bids fell between $420.00 and $613.25.
- Owner
- North Carolina DOT
- Item
- 0408000000-E
- Unit
- LF
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 2 | 2 | $127.50 | 20 | $146.97 |
| 2014 | 9 | 9 | $155.00 | 65 | $150.00 |
| 2015 | 8 | 8 | $170.89 | 51 | $190.00 |
| 2016 | 3 | 3 | $195.00 | 22 | $197.50 |
| 2017 | 4 | 4 | $251.45 | 32 | $200.00 |
| 2018 | 5 | 5 | $360.00 | 26 | $313.50 |
| 2019 | 1 | 1 | $309.70 | 4 | $280.50 |
| 2021 | 6 | 6 | $361.00 | 18 | $335.00 |
| 2022 | 8 | 8 | $389.85 | 34 | $400.19 |
| 2023 | 4 | 4 | $490.00 | 20 | $466.95 |
| 2024 | 1 | 1 | $460.00 | 5 | $500.00 |
| 2025 | 2 | 2 | $409.70 | 9 | $463.90 |
| 2026 | 2 | 2 | $528.22 | 11 | $550.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 4 | $259.40 | 29 | $205.00 |
| Cumberland | 3 | $280.00 | 19 | $170.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 8 to 84 | 13 | $363.81 |
| 92 to 164 | 14 | $326.32 |
| 176 to 344 | 14 | $193.48 |
| 344 to 1,420 | 14 | $251.45 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C204338 | Wake | 148 | $322.44 | $560.28 | 8 | BLYTHE CONSTRUCTION INC | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 164 | $734.00 | $410.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 17 JUN 2025 | C204898 | Wake | 84 | $445.00 | $463.90 | 5 | CARDINAL CIVIL CONTRACTING LLC | NCDOT |
| 21 JAN 2025 | C204992 | Hoke | 16 | $374.40 | $511.00 | 4 | BARNHILL CONTRACTING CO | NCDOT |
| 17 DEC 2024 | C204821 | Guilford | 24 | $460.00 | $500.00 | 5 | YATES CONSTRUCTION CO INC | NCDOT |
| 19 DEC 2023 | C204887 | Cherokee | 184 | $540.00 | $510.00 | 2 | WRIGHT BROTHERS CONSTRUCTION COMPANY INC | NCDOT |
| 21 NOV 2023 | C204904 | Transylvania | 128 | $850.00 | $449.10 | 4 | MOUNTAIN CREEK CONTRACTORS INC | NCDOT |
| 18 JUL 2023 | C204851 | Cleveland | 204 | $435.00 | $500.50 | 4 | AMES CONSTRUCTION INC | NCDOT |
| 21 FEB 2023 | C204772 | Robeson | 92 | $440.00 | $450.00 | 10 | C M LINDSAY & SONS INC | NCDOT |
| 20 DEC 2022 | C204812 | Graham | 80 | $700.00 | $700.68 | 2 | ADAMS CONTRACTING CO INC | NCDOT |
| 18 OCT 2022 | C204746 | Forsyth | 748 | $450.00 | $400.38 | 7 | FLATIRON CONSTRUCTORS INC | NCDOT |
| 16 AUG 2022 | C204731 | Graham | 92 | $550.00 | $550.00 | 6 | WATSON CONTRACTING INC | NCDOT |
| 19 JUL 2022 | C204728 | Robeson | 1,420 | $301.51 | $375.00 | 3 | WEBBER LLC | NCDOT |
| 19 JUL 2022 | C204708 | Union | 24 | $383.70 | $425.00 | 4 | BLYTHE DEVELOPMENT CO | NCDOT |
| 21 JUN 2022 | C204110 | Cumberland | 1,292 | $396.00 | $342.50 | 6 | BRANCH CIVIL INC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way