Ext loop emulator process unit unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $6,595.00 per EACH for item 7481260000-N, ext loop emulator process unit, over the 24 months to 20 OCT 2026, across 24 low bids. Half of all 119 bids fell between $4,890.00 and $11,930.
- Owner
- North Carolina DOT
- Item
- 7481260000-N
- Unit
- EACH
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 2 | 2 | $5,714.00 | 10 | $7,000.00 |
| 2014 | 2 | 2 | $7,626.40 | 8 | $8,210.00 |
| 2015 | 2 | 2 | $6,700.00 | 17 | $6,000.00 |
| 2016 | 1 | 1 | $7,187.98 | 8 | $6,550.00 |
| 2017 | 5 | 5 | $6,500.00 | 33 | $5,490.40 |
| 2018 | 7 | 7 | $8,675.00 | 28 | $8,019.31 |
| 2019 | 4 | 4 | $5,764.00 | 19 | $6,875.00 |
| 2020 | 2 | 2 | $4,750.00 | 8 | $7,096.50 |
| 2021 | 8 | 8 | $6,161.32 | 32 | $6,161.32 |
| 2022 | 4 | 4 | $7,965.50 | 13 | $8,540.00 |
| 2023 | 16 | 16 | $5,750.00 | 65 | $5,800.00 |
| 2024 | 10 | 9 | $5,565.00 | 38 | $6,275.00 |
| 2025 | 12 | 12 | $6,500.00 | 46 | $6,549.49 |
| 2026 | 9 | 9 | $7,036.08 | 61 | $6,690.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Wake | 3 | $7,036.08 | 18 | $6,447.00 |
| Forsyth | 3 | $3,283.35 | 13 | $3,283.35 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 6 | $5,987.50 |
| 1 to 2 | 6 | $6,407.50 |
| 2 to 4 | 6 | $6,375.00 |
| 4 to 7 | 6 | $9,003.31 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C204338 | Wake | 2 | $14,000 | $6,889.68 | 8 | BLYTHE CONSTRUCTION INC | NCDOT |
| 15 SEP 2026 | C204990 | Randolph | 1 | $6,690.00 | $6,690.00 | 9 | APAC ATLANTIC INC THOMPSON ARTHUR DIVISION | NCDOT |
| 15 SEP 2026 | C204947 | Caldwell | 4 | $15,732 | $15,732 | 3 | BRANCH CIVIL INC | NCDOT |
| 16 JUN 2026 | C205160 | Forsyth | 2 | $3,283.35 | $3,283.35 | 5 | BLYTHE CONSTRUCTION INC | NCDOT |
| 16 JUN 2026 | C205157 | Randolph | 2 | $6,125.00 | $5,940.00 | 11 | BRANCH CIVIL INC | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 4 | $10,634 | $13,150 | 10 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 17 MAR 2026 | C204512 | Wake | 5 | $7,036.08 | $6,447.00 | 4 | CONTI CIVIL LLC | NCDOT |
| 17 MAR 2026 | C205038 | Wake | 1 | $4,500.00 | $4,590.00 | 6 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 20 JAN 2026 | C205117 | Cabarrus | 1 | $7,475.00 | $6,505.00 | 5 | NJR GROUP INC | NCDOT |
| 16 DEC 2025 | C205018 | Rockingham | 4 | $3,200.00 | $3,354.77 | 6 | SMITH-ROWE, LLC | NCDOT |
| 18 NOV 2025 | C205012 | Forsyth | 7 | $3,000.00 | $3,000.00 | 5 | APAC ATLANTIC INC SMITH ROWE LLC JV | NCDOT |
| 21 OCT 2025 | C204840 | Caldwell | 2 | $20,440 | $19,470 | 4 | HEI CIVIL CAROLINAS LLC | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 5 | $17,643 | $17,821 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 16 SEP 2025 | C205042 | Moore | 1 | $3,500.00 | $3,500.00 | 3 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 16 SEP 2025 | C205099 | Surry | 1 | $1,630.00 | $17,200 | 4 | SMITH-ROWE, LLC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way