Fire hydrant leg unit price, North Carolina

Low bidders on NCDOT contracts carried a median of $144.00 per LF for item 5673000000-E, fire hydrant leg, over the 24 months to 20 OCT 2026, across 62 low bids. Half of all 340 bids fell between $110.49 and $205.35.

Owner
North Carolina DOT
Item
5673000000-E
Unit
LF
Latest letting
20 OCT 2026
$144.00Low bidder's median, per LF
$150.00Median of all bids, per LF
62Contracts in the window

By year of letting

Fire hydrant leg, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20181313$52.6054$59.50
20191313$65.0053$95.00
202033$133.0511$133.05
20211818$81.8081$80.00
20223131$118.80133$138.00
20232525$130.00108$138.50
20242423$125.00114$142.44
20253232$125.00170$146.25
20262222$155.50135$155.00
Fire hydrant leg, NCDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Fire hydrant leg, NCDOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Mecklenburg6$144.0041$176.50
Wake5$160.0031$170.00
Forsyth5$177.2030$144.43
Guilford5$140.0025$155.00
Wayne3$155.0020$122.50
Cumberland3$90.0012$90.00
Fire hydrant leg, NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Fire hydrant leg, NCDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
5 to 2015$155.00
20 to 7616$137.50
84 to 15515$140.00
159 to 1,17016$137.50
Fire hydrant leg, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NCDOT contracts carrying Fire hydrant leg
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C204338Wake326$145.00$170.008BLYTHE CONSTRUCTION INCNCDOT
15 SEP 2026C205206Onslow13$110.65$113.773BARNHILL CONTRACTING CONCDOT
15 SEP 2026C204990Randolph124$106.71$150.009APAC ATLANTIC INC THOMPSON ARTHUR DIVISIONNCDOT
15 SEP 2026C205214Wilkes17$252.00$252.005JAMES R VANNOY & SONS CONSTRUCTION COMPANY, LLCNCDOT
15 SEP 2026C204947Caldwell159$153.00$144.743BRANCH CIVIL INCNCDOT
18 AUG 2026C205202Guilford63$120.00$120.005TRIANGLE GRADING & PAVING INCNCDOT
18 AUG 2026C204504Watauga11$140.50$140.503BRANCH CIVIL INCNCDOT
18 AUG 2026C205219Rutherford196$113.00$113.001WRIGHT BROTHERS CIVIL CONSTRUCTION LLCNCDOT
16 JUN 2026C205157Randolph144$161.00$145.6011BRANCH CIVIL INCNCDOT
19 MAY 2026C205106Hyde, Beaufort8$265.00$240.005S T WOOTEN CORPORATIONNCDOT
19 MAY 2026C204733Yadkin20$190.53$159.234BLYTHE CONSTRUCTION INCNCDOT
19 MAY 2026C204773Gaston, Mecklenburg20$229.26$237.1310ZACHRY CONSTRUCTION CORPORATIONNCDOT
21 APR 2026C205130Wayne169$156.00$156.005BRANCH CIVIL INCNCDOT
21 APR 2026C204857Johnston51$150.00$150.007SUNROCK INDUSTRIES LLC DBA CAROLINA SUNROCK LLCNCDOT
17 MAR 2026C204512Wake1,170$160.00$215.004CONTI CIVIL LLCNCDOT
Latest NCDOT contracts carrying Fire hydrant leg

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy