Generic grading item (ton) - aggregate shoulder borrow unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $20.00 per TON for item 0255000000-E, generic grading item (ton) - aggregate shoulder borrow, from 18 JUN 2013 to 16 JUL 2024, across 90 low bids. Half of all 245 bids fell between $19.00 and $30.00.
- Owner
- North Carolina DOT
- Item
- 0255000000-E
- Unit
- TON
- Latest letting
- 16 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 18 | 18 | $20.00 | 52 | $21.00 |
| 2014 | 12 | 12 | $20.00 | 37 | $24.75 |
| 2015 | 14 | 14 | $20.00 | 35 | $21.00 |
| 2016 | 28 | 27 | $21.00 | 71 | $22.00 |
| 2017 | 17 | 17 | $24.00 | 45 | $29.00 |
| 2022 | 1 | 1 | $45.40 | 3 | $39.00 |
| 2024 | 1 | 1 | $25.00 | 2 | $41.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Robeson | 7 | $20.00 | 22 | $38.25 |
| Gaston | 5 | $30.00 | 20 | $23.75 |
| Lincoln | 4 | $20.00 | 15 | $21.00 |
| Catawba | 5 | $20.00 | 14 | $20.00 |
| Chatham | 5 | $15.00 | 12 | $16.85 |
| Randolph | 3 | $15.00 | 12 | $25.00 |
| Bladen, Columbus | 4 | $24.58 | 11 | $25.05 |
| Pender | 4 | $44.90 | 11 | $42.40 |
| Iredell | 6 | $23.25 | 10 | $24.50 |
| Cumberland, Harnett | 3 | $20.00 | 10 | $21.15 |
| Columbus | 3 | $25.00 | 10 | $28.50 |
| Richmond | 4 | $12.88 | 8 | $11.78 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 1.50 to 1,620 | 22 | $25.00 |
| 1,650 to 3,407 | 23 | $20.00 |
| 3,465 to 5,892 | 22 | $20.50 |
| 5,901 to 21,806 | 23 | $21.30 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 16 JUL 2024 | C204948 | Iredell | 8,745 | $25.00 | $41.00 | 2 | MAYMEAD INC | NCDOT |
| 21 JUN 2022 | C204720 | Pender | 18,820 | $45.40 | $39.00 | 3 | S T WOOTEN CORPORATION | NCDOT |
| 17 OCT 2017 | C204090 | Pender | 85 | $52.13 | $52.00 | 3 | S T WOOTEN CORPORATION | NCDOT |
| 17 OCT 2017 | C204091 | Wake | 915 | $45.00 | $34.00 | 2 | THE LANE CONSTRUCTION CORPORATION | NCDOT |
| 19 SEP 2017 | C204087 | Durham | 1,570 | $16.70 | $33.50 | 4 | CAROLINA SUNROCK LLC | NCDOT |
| 19 SEP 2017 | C204083 | Granville | 7,284 | $18.78 | $19.44 | 2 | CAROLINA SUNROCK LLC | NCDOT |
| 15 AUG 2017 | C204052 | Sampson | 4,930 | $38.40 | $38.40 | 1 | BARNHILL CONTRACTING COMPANY | NCDOT |
| 15 AUG 2017 | C204046 | Chatham | 14,636 | $20.00 | $19.50 | 2 | S T WOOTEN CORPORATION | NCDOT |
| 16 MAY 2017 | C204018 | Scotland, Hoke | 3,475 | $19.00 | $18.50 | 2 | HUDSON PAVING, INC. | NCDOT |
| 16 MAY 2017 | C204019 | Randolph | 17,434 | $26.00 | $25.73 | 2 | RILEY PAVING INC | NCDOT |
| 16 MAY 2017 | C204022 | Catawba | 3,465 | $19.00 | $19.00 | 3 | MIDSTATE CONTRACTORS INC | NCDOT |
| 16 MAY 2017 | C204016 | Gaston | 9,808 | $30.00 | $25.00 | 3 | ASPHALT PAVING OF SHELBY INC | NCDOT |
| 16 MAY 2017 | C204009 | Iredell | 7,287 | $24.00 | $24.00 | 1 | MAYMEAD, INC. | NCDOT |
| 18 APR 2017 | C204008 | Cleveland | 7,081 | $30.00 | $27.50 | 2 | ASPHALT PAVING OF SHELBY INC | NCDOT |
| 21 MAR 2017 | C203877 | Robeson | 40 | $65.00 | $65.00 | 10 | S T WOOTEN CORPORATION | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.