Low bidders on NCDOT contracts carried a median of $161.00 per SY for item 8893000000-E, generic structure item (sy) - hydro-demolition of bridge deck, over the 24 months to 20 OCT 2026, across 5 low bids. Half of all 29 bids fell between $135.00 and $195.00.
- Owner
- North Carolina DOT
- Item
- 8893000000-E
- Unit
- SY
- Latest letting
- 16 DEC 2025
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 4 | 4 | $69.17 | 17 | $75.00 |
| 2014 | 3 | 3 | $28.30 | 13 | $41.00 |
| 2015 | 2 | 2 | $72.50 | 9 | $72.95 |
| 2016 | 5 | 5 | $80.00 | 12 | $80.00 |
| 2017 | 3 | 3 | $100.00 | 5 | $100.00 |
| 2018 | 7 | 6 | $62.48 | 27 | $80.00 |
| 2019 | 3 | 3 | $65.00 | 17 | $78.00 |
| 2020 | 1 | 1 | $29.00 | 8 | $162.50 |
| 2021 | 4 | 4 | $100.00 | 17 | $65.00 |
| 2022 | 5 | 5 | $100.00 | 17 | $98.00 |
| 2023 | 5 | 5 | $115.00 | 26 | $155.69 |
| 2024 | 2 | 2 | $180.00 | 10 | $186.50 |
| 2025 | 5 | 5 | $161.00 | 29 | $165.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Buncombe | 7 | $110.00 | 30 | $110.00 |
| Mecklenburg | 3 | $130.00 | 13 | $200.00 |
| Cumberland | 3 | $85.00 | 6 | $85.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 236 to 1,823.80 | 12 | $107.50 |
| 1,930 to 3,520 | 12 | $112.50 |
| 3,620.80 to 7,398 | 12 | $70.00 |
| 7,662.30 to 17,000 | 12 | $55.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 16 DEC 2025 | C205090 | Wilson | 597.60 | $161.00 | $195.00 | 5 | SAFFO CONTRACTORS INC | NCDOT |
| 18 NOV 2025 | C204967 | Wake | 4,522.40 | $165.00 | $167.50 | 2 | AMERICAN CONTRACTING & SERVICES INC | NCDOT |
| 21 OCT 2025 | C205011 | Buncombe | 1,823.80 | $130.00 | $180.00 | 7 | LORR CONSTRUCTION, INC. | NCDOT |
| 17 JUN 2025 | C204454 | Buncombe | 2,055 | $146.00 | $103.00 | 7 | FREYSSINET INC | NCDOT |
| 15 APR 2025 | C204567 | Ashe | 3,143.60 | $171.00 | $165.50 | 8 | SAFFO CONTRACTORS INC | NCDOT |
| 16 JUL 2024 | C204843 | Randolph | 236 | $250.00 | $343.85 | 4 | CONTI CIVIL LLC | NCDOT |
| 18 JUN 2024 | C204455 | Chatham, Moore | 3,255.60 | $110.00 | $130.00 | 6 | FREYSSINET INC | NCDOT |
| 17 OCT 2023 | C204488 | Cherokee | 3,137 | $83.00 | $100.00 | 7 | BUCKEYE BRIDGE LLC | NCDOT |
| 20 JUN 2023 | C204838 | Edgecombe | 896 | $130.00 | $152.00 | 4 | BARNHILL CONTRACTING CO | NCDOT |
| 16 MAY 2023 | C204237 | Mecklenburg | 7,662.30 | $240.00 | $240.00 | 7 | MOUNTAIN CREEK CONTRACTORS INC | NCDOT |
| 18 APR 2023 | C204726 | Buncombe | 9,299 | $100.00 | $100.00 | 3 | APAC ATLANTIC INC DBA HARRISON CONSTRUCTION COMPANY | NCDOT |
| 17 JAN 2023 | C204804 | Iredell, Catawba | 750 | $115.00 | $161.38 | 5 | MOUNTAIN CREEK CONTRACTORS INC | NCDOT |
| 19 JUL 2022 | C204453 | Edgecombe, Nash | 3,688 | $140.00 | $99.00 | 4 | AMERICAN CONTRACTING & SERVICES INC | NCDOT |
| 19 JUL 2022 | C204655 | Wake | 11,381 | $32.00 | $104.94 | 3 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 17 MAY 2022 | C204709 | Madison | 17,000 | $53.00 | $53.00 | 5 | BUCKEYE BRIDGE LLC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.