Mill asp pvmt *****" dth - (2-1/2") unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $4.65 per SY for item 1297000000-E, mill asp pvmt *****" dth - (2-1/2"), over the 24 months to 20 OCT 2026, across 14 low bids. Half of all 67 bids fell between $3.23 and $6.22.
- Owner
- North Carolina DOT
- Item
- 1297000000-E
- Unit
- SY
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 16 | 15 | $1.35 | 58 | $1.77 |
| 2014 | 7 | 7 | $1.31 | 25 | $1.50 |
| 2015 | 10 | 10 | $1.68 | 33 | $2.15 |
| 2016 | 5 | 5 | $1.81 | 11 | $1.90 |
| 2017 | 1 | 1 | $1.70 | 2 | $1.85 |
| 2018 | 9 | 9 | $2.87 | 22 | $2.94 |
| 2019 | 1 | 1 | $2.05 | 2 | $2.35 |
| 2021 | 5 | 5 | $2.40 | 19 | $2.76 |
| 2022 | 5 | 5 | $3.00 | 22 | $8.00 |
| 2023 | 1 | 1 | $3.05 | 5 | $3.05 |
| 2024 | 6 | 6 | $4.03 | 24 | $3.75 |
| 2025 | 5 | 5 | $6.00 | 23 | $5.40 |
| 2026 | 6 | 6 | $4.20 | 32 | $4.88 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 870 to 2,200 | 3 | $8.25 |
| 2,760 to 7,050 | 4 | $6.00 |
| 21,540 to 46,075 | 3 | $2.70 |
| 48,180 to 150,280 | 4 | $3.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205207 | Pender | 870 | $13.00 | $11.85 | 5 | S T WOOTEN CORPORATION | NCDOT |
| 15 SEP 2026 | C204349 | Wake, Durham | 88,481 | $3.25 | $3.95 | 4 | BLYTHE CONSTRUCTION INC | NCDOT |
| 19 MAY 2026 | C205138 | Mecklenburg, Iredell | 2,760 | $8.40 | $9.20 | 4 | KING ASPHALT INC | NCDOT |
| 21 APR 2026 | C204857 | Johnston | 21,540 | $3.40 | $4.25 | 7 | SUNROCK INDUSTRIES LLC DBA CAROLINA SUNROCK LLC | NCDOT |
| 21 APR 2026 | C205088 | Wake, Franklin | 7,050 | $5.00 | $5.00 | 4 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 17 FEB 2026 | C205035 | Wayne | 46,075 | $2.70 | $3.62 | 8 | BRANCH CIVIL INC | NCDOT |
| 21 OCT 2025 | C205034 | Northampton | 150,280 | $1.25 | $1.98 | 2 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 6,130 | $6.00 | $6.00 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 16 SEP 2025 | C205040 | Onslow | 2,200 | $7.50 | $7.50 | 1 | BARNHILL CONTRACTING CO | NCDOT |
| 15 JUL 2025 | C204421 | Craven | 1,200 | $8.25 | $15.00 | 5 | S T WOOTEN CORPORATION | NCDOT |
| 20 MAY 2025 | C205032 | Chatham | 6,150 | $6.00 | $5.08 | 12 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 17 DEC 2024 | C204854 | Gates, Pasquotank | 48,180 | $3.75 | $3.75 | 3 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 19 NOV 2024 | C204995 | Wake | 25,697 | $1.35 | $2.52 | 4 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 19 NOV 2024 | C204949 | Moore | 87,890 | $4.30 | $3.50 | 5 | S T WOOTEN CORPORATION | NCDOT |
| 15 OCT 2024 | C204348 | Iredell, Catawba | 44,570 | $5.60 | $4.00 | 5 | BLYTHE DEVELOPMENT LLC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.