Og asp frict fc-1 mod unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $152.50 per TON for item 1662000000-E, og asp frict fc-1 mod, over the 24 months to 20 OCT 2026, across 3 low bids. Half of all 14 bids fell between $153.12 and $369.98.
- Owner
- North Carolina DOT
- Item
- 1662000000-E
- Unit
- TON
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 2 | 2 | $44.90 | 5 | $46.50 |
| 2014 | 2 | 2 | $72.50 | 5 | $90.00 |
| 2015 | 1 | 1 | $58.00 | 3 | $136.47 |
| 2016 | 4 | 4 | $79.08 | 7 | $80.00 |
| 2017 | 3 | 3 | $79.50 | 11 | $96.00 |
| 2018 | 5 | 5 | $84.94 | 11 | $111.79 |
| 2019 | 7 | 7 | $72.00 | 18 | $73.50 |
| 2020 | 4 | 4 | $83.00 | 14 | $83.31 |
| 2021 | 9 | 9 | $103.50 | 26 | $98.75 |
| 2022 | 8 | 8 | $91.12 | 17 | $91.25 |
| 2023 | 10 | 10 | $97.00 | 35 | $116.00 |
| 2024 | 3 | 3 | $362.00 | 12 | $338.43 |
| 2025 | 1 | 1 | $439.87 | 8 | $364.95 |
| 2026 | 2 | 2 | $117.25 | 6 | $148.74 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Haywood | 10 | $267.00 | 29 | $338.00 |
| Guilford | 7 | $90.46 | 24 | $102.00 |
| Polk | 4 | $130.50 | 16 | $109.00 |
| Johnston | 5 | $91.25 | 14 | $123.25 |
| Richmond | 4 | $87.75 | 11 | $80.00 |
| Wilson | 4 | $71.05 | 8 | $71.05 |
| Edgecombe | 3 | $70.00 | 6 | $68.50 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 145 to 1,110 | 15 | $155.62 |
| 1,115 to 6,386 | 15 | $91.25 |
| 6,440 to 11,624 | 15 | $83.00 |
| 11,659 to 56,912 | 16 | $71.17 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205246 | Polk | 10,606 | $152.50 | $153.75 | 4 | ROGERS GROUP INC | NCDOT |
| 17 MAR 2026 | C205156 | Wilson | 6,440 | $82.00 | $88.50 | 2 | S T WOOTEN CORPORATION | NCDOT |
| 17 JUN 2025 | C205015 | Haywood | 1,260 | $439.87 | $364.95 | 8 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 16 JUL 2024 | C204884 | Haywood | 800 | $362.00 | $349.05 | 4 | WRIGHT BROTHERS CONSTRUCTION COMPANY INC | NCDOT |
| 16 JUL 2024 | C204865 | Haywood | 1,100 | $351.00 | $340.75 | 3 | WRIGHT BROTHERS CONSTRUCTION COMPANY INC | NCDOT |
| 28 MAY 2024 | C204796 | Haywood | 580 | $386.02 | $334.10 | 5 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 19 DEC 2023 | C204684 | Haywood | 920 | $360.89 | $288.87 | 4 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 21 NOV 2023 | C204866 | Brunswick | 10,862 | $97.00 | $100.05 | 4 | HIGHLAND PAVING CO LLC | NCDOT |
| 21 NOV 2023 | C204873 | Johnston | 1,880 | $118.20 | $120.25 | 5 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 18 JUL 2023 | C204833 | New Hanover, Pender | 28,453 | $97.00 | $97.00 | 3 | S T WOOTEN CORPORATION | NCDOT |
| 18 JUL 2023 | C204820 | Nash | 16,090 | $68.90 | $70.00 | 3 | S T WOOTEN CORPORATION | NCDOT |
| 16 MAY 2023 | C204818 | Edgecombe | 18,120 | $75.00 | $71.00 | 2 | BARNHILL CONTRACTING CO | NCDOT |
| 16 MAY 2023 | C204819 | Edgecombe | 18,430 | $70.00 | $72.80 | 2 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 18 APR 2023 | C204736 | Guilford | 11,659 | $90.46 | $104.00 | 3 | VECELLIO & GROGAN INC DBA SHARPE BROTHERS | NCDOT |
| 18 APR 2023 | C204793 | Rockingham | 340 | $200.55 | $200.00 | 7 | W C ENGLISH INCORPORATED | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.