Overhead footing unit price, North Carolina

Low bidders on NCDOT contracts carried a median of $2,500.00 per CY for item 4057000000-E, overhead footing, over the 24 months to 20 OCT 2026, across 7 low bids. Half of all 36 bids fell between $1,162.00 and $2,697.42.

Owner
North Carolina DOT
Item
4057000000-E
Unit
CY
Latest letting
17 MAR 2026
$2,500.00Low bidder's median, per CY
$2,348.93Median of all bids, per CY
7Contracts in the window

By year of letting

Overhead footing, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201366$950.0037$1,214.00
201499$875.0056$882.50
201577$1,425.0039$1,245.00
201622$1,053.0012$936.00
201799$1,400.0058$1,197.50
201877$1,155.0035$1,155.00
201966$1,210.3031$1,167.87
202188$1,510.0032$975.00
202277$2,000.0027$2,000.00
202366$1,834.9524$1,828.00
202433$2,000.0012$1,809.50
202555$2,780.0030$2,500.00
202622$1,831.006$1,298.00
Overhead footing, NCDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Overhead footing, NCDOT: unit prices by county, all lettings
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Guilford10$1,192.4563$1,000.00
Forsyth7$1,744.0045$1,250.00
Wake6$1,073.0033$1,217.98
Mecklenburg4$1,000.0017$1,050.00
Cumberland3$850.0017$899.97
Johnston3$1,500.0014$1,170.00
Robeson3$2,000.009$1,434.00
Overhead footing, NCDOT: unit prices by county, all lettings

Countys with at least three low bids, over all lettings.

By quantity

Overhead footing, NCDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
6 to 3619$1,500.00
36 to 6619$1,162.00
70 to 17219$1,184.90
188 to 72720$1,235.30
Overhead footing, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NCDOT contracts carrying Overhead footing
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
17 MAR 2026C204996Cumberland, Robeson54$2,500.00$2,075.002FULCHER ELECTRIC OF FAYETTEVILLE INCNCDOT
17 FEB 2026C205036Robeson45$1,162.00$1,162.004BARNHILL CONTRACTING CONCDOT
18 NOV 2025C205012Forsyth85$3,500.00$2,800.005APAC ATLANTIC INC SMITH ROWE LLC JVNCDOT
21 OCT 2025C205093Davie17$2,780.00$2,500.0010BRANCH CIVIL INCNCDOT
19 AUG 2025C204975Forsyth33$2,200.00$2,200.003BLYTHE CONSTRUCTION INCNCDOT
15 JUL 2025C205072New Hanover, Pender418$150.00$155.007S T WOOTEN CORPORATIONNCDOT
17 JUN 2025C205037Davidson9$3,000.00$2,679.895SMITH-ROWE, LLCNCDOT
15 OCT 2024C204348Iredell, Catawba333$2,100.00$1,819.005BLYTHE DEVELOPMENT LLCNCDOT
16 JUL 2024C204878Buncombe375$1,315.00$1,650.003ARCHER WRIGHT JVNCDOT
16 JUL 2024C204843Randolph132$2,000.00$2,050.004CONTI CIVIL LLCNCDOT
19 DEC 2023C204684Haywood48$200.00$203.094ZACHRY CONSTRUCTION CORPORATIONNCDOT
21 NOV 2023C204873Johnston24$1,669.90$1,450.005ZACHRY CONSTRUCTION CORPORATIONNCDOT
21 NOV 2023C204852Iredell125$2,230.00$2,200.005THE LANE CONSTRUCTION CORPORATIONNCDOT
18 JUL 2023C204851Cleveland172$2,000.00$2,000.004AMES CONSTRUCTION INCNCDOT
18 JUL 2023C204786Wake36$2,100.00$2,000.004CONTI CIVIL LLCNCDOT
Latest NCDOT contracts carrying Overhead footing

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy