Paint pvt mkg symbol unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $60.00 per EACH for item 4845000000-N, paint pvt mkg symbol, over the 24 months to 20 OCT 2026, across 120 low bids. Half of all 515 bids fell between $45.00 and $75.00.
- Owner
- North Carolina DOT
- Item
- 4845000000-N
- Unit
- EACH
- Latest letting
- 20 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 56 | 56 | $35.00 | 227 | $40.00 |
| 2014 | 44 | 44 | $40.00 | 219 | $48.72 |
| 2015 | 50 | 50 | $50.00 | 207 | $53.50 |
| 2016 | 51 | 51 | $45.00 | 158 | $45.50 |
| 2017 | 36 | 36 | $46.87 | 149 | $54.29 |
| 2018 | 80 | 80 | $55.00 | 261 | $55.00 |
| 2019 | 39 | 39 | $50.00 | 128 | $50.00 |
| 2020 | 23 | 23 | $25.00 | 96 | $35.00 |
| 2021 | 52 | 52 | $50.00 | 182 | $50.00 |
| 2022 | 49 | 49 | $50.00 | 170 | $50.00 |
| 2023 | 46 | 46 | $61.23 | 182 | $63.90 |
| 2024 | 47 | 46 | $50.00 | 182 | $50.77 |
| 2025 | 61 | 61 | $55.00 | 255 | $57.43 |
| 2026 | 44 | 44 | $70.00 | 203 | $63.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Wake | 9 | $50.00 | 49 | $50.00 |
| Randolph | 6 | $56.38 | 38 | $55.00 |
| Forsyth | 7 | $50.00 | 37 | $55.00 |
| Chatham | 5 | $50.00 | 34 | $52.25 |
| Wayne | 4 | $63.88 | 26 | $65.22 |
| Cumberland | 5 | $66.50 | 18 | $62.30 |
| Davidson | 3 | $109.66 | 17 | $111.00 |
| Mecklenburg | 4 | $56.50 | 17 | $72.00 |
| Moore | 4 | $60.00 | 15 | $60.00 |
| Alamance | 4 | $52.48 | 13 | $45.00 |
| Rockingham | 3 | $68.86 | 13 | $68.86 |
| Guilford | 3 | $46.00 | 12 | $48.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 18 | 30 | $60.00 |
| 20 to 51 | 30 | $58.50 |
| 52 to 120 | 30 | $62.00 |
| 126 to 516 | 30 | $50.60 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205216 | Martin | 70 | $73.00 | $73.00 | 4 | BARNHILL CONTRACTING CO | NCDOT |
| 20 OCT 2026 | C204338 | Wake | 258 | $35.00 | $35.00 | 8 | BLYTHE CONSTRUCTION INC | NCDOT |
| 20 OCT 2026 | C205247 | Rowan | 167 | $63.78 | $63.78 | 2 | NJR GROUP INC | NCDOT |
| 24 SEP 2026 | C205140 | New Hanover | 72 | $84.69 | $84.69 | 1 | BALFOUR BEATTY INFRASTRUCTURE INC | NCDOT |
| 15 SEP 2026 | C205206 | Onslow | 51 | $70.00 | $70.00 | 3 | BARNHILL CONTRACTING CO | NCDOT |
| 15 SEP 2026 | C205203 | Wayne | 2 | $35.00 | $100.00 | 6 | LEGION ASPHALT INC | NCDOT |
| 15 SEP 2026 | C204349 | Wake, Durham | 200 | $30.00 | $30.00 | 4 | BLYTHE CONSTRUCTION INC | NCDOT |
| 15 SEP 2026 | C204990 | Randolph | 32 | $77.00 | $77.00 | 9 | APAC ATLANTIC INC THOMPSON ARTHUR DIVISION | NCDOT |
| 15 SEP 2026 | C205214 | Wilkes | 8 | $97.00 | $97.00 | 5 | JAMES R VANNOY & SONS CONSTRUCTION COMPANY, LLC | NCDOT |
| 15 SEP 2026 | C204947 | Caldwell | 170 | $66.65 | $70.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 AUG 2026 | C205195 | Catawba | 21 | $51.28 | $52.14 | 4 | BLYTHE DEVELOPMENT LLC | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 24 | $119.00 | $119.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 AUG 2026 | C205219 | Rutherford | 75 | $112.00 | $112.00 | 1 | WRIGHT BROTHERS CIVIL CONSTRUCTION LLC | NCDOT |
| 21 JUL 2026 | C205183 | Nash | 1 | $125.00 | $125.00 | 2 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 16 JUN 2026 | C205160 | Forsyth | 39 | $55.00 | $55.00 | 5 | BLYTHE CONSTRUCTION INC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way