Pile drv equip setup ** steel piles - (hp 14 x 73) unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $2,500.00 per EACH for item 8328200000-E, pile drv equip setup ** steel piles - (hp 14 x 73), over the 24 months to 20 OCT 2026, across 13 low bids. Half of all 77 bids fell between $1,000.00 and $3,505.50.
- Owner
- North Carolina DOT
- Item
- 8328200000-E
- Unit
- EACH
- Latest letting
- 18 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2017 | 1 | 1 | $1,500.00 | 4 | $637.50 |
| 2018 | 4 | 4 | $475.00 | 22 | $675.00 |
| 2019 | 3 | 3 | $588.31 | 16 | $871.58 |
| 2020 | 1 | 1 | $1,200.00 | 9 | $915.86 |
| 2021 | 8 | 7 | $587.96 | 40 | $1,000.00 |
| 2022 | 13 | 12 | $2,150.00 | 58 | $2,000.00 |
| 2023 | 4 | 4 | $1,890.12 | 17 | $1,820.00 |
| 2024 | 6 | 5 | $1,725.00 | 40 | $1,925.00 |
| 2025 | 6 | 6 | $1,372.93 | 42 | $1,637.50 |
| 2026 | 7 | 7 | $2,931.24 | 35 | $2,764.70 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 6 to 14 | 3 | $2,500.00 |
| 19 to 26 | 3 | $3,774.93 |
| 34 to 40 | 3 | $2,130.87 |
| 42 to 148 | 4 | $2,057.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 18 AUG 2026 | C205205 | Robeson | 12 | $2,500.00 | $1,925.00 | 2 | BMCO CONSTRUCTION INC | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 14 | $1,979.50 | $1,979.50 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 AUG 2026 | C205070 | Rutherford | 26 | $5,000.00 | $2,500.00 | 9 | UNITED INFRASTRUCTURE GROUP INC | NCDOT |
| 16 JUN 2026 | C205160 | Forsyth | 40 | $500.00 | $600.00 | 5 | BLYTHE CONSTRUCTION INC | NCDOT |
| 19 MAY 2026 | C205187 | Cumberland | 62 | $3,500.00 | $3,500.00 | 4 | HIGHLAND PAVING CO LLC | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 42 | $4,880.41 | $3,250.00 | 10 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 20 JAN 2026 | C205129 | Pamlico | 6 | $2,931.24 | $26,466 | 2 | SMITH-ROWE, LLC | NCDOT |
| 21 OCT 2025 | C205093 | Davie | 34 | $3,300.00 | $1,634.49 | 10 | BRANCH CIVIL INC | NCDOT |
| 19 AUG 2025 | C204956 | Burke, Caldwell | 26 | $3,774.93 | $3,774.93 | 3 | BALFOUR BEATTY INFRASTRUCTURE INC | NCDOT |
| 15 JUL 2025 | C205072 | New Hanover, Pender | 148 | $570.00 | $3,300.00 | 7 | S T WOOTEN CORPORATION | NCDOT |
| 17 JUN 2025 | C205037 | Davidson | 34 | $2,130.87 | $2,130.87 | 5 | SMITH-ROWE, LLC | NCDOT |
| 20 MAY 2025 | C205032 | Chatham | 70 | $615.00 | $1,000.00 | 9 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 18 MAR 2025 | C204766 | Madison | 19 | $500.00 | $1,240.00 | 8 | KEMP SIGMON CONSTRUCTION CO INC | NCDOT |
| 15 OCT 2024 | C204339 | Wake | 20 | n/a | $5,650.64 | 6 | NCDOT | |
| 20 AUG 2024 | C204925 | Haywood | 24 | $1,015.00 | $1,015.00 | 7 | NHM CONSTRUCTORS INC | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.