Low bidders on NCDOT contracts carried a median of $1,120.00 per EACH for item 8114000000-N, spt testing, over the 24 months to 20 OCT 2026, across 7 low bids. Half of all 34 bids fell between $1,000.00 and $2,352.50.
- Owner
- North Carolina DOT
- Item
- 8114000000-N
- Unit
- EACH
- Latest letting
- 15 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 33 | 33 | $860.00 | 169 | $1,000.00 |
| 2014 | 17 | 17 | $1,000.00 | 113 | $1,000.00 |
| 2015 | 7 | 7 | $1,125.00 | 46 | $1,287.50 |
| 2016 | 9 | 9 | $500.00 | 54 | $557.50 |
| 2017 | 4 | 4 | $1,500.00 | 33 | $1,080.00 |
| 2018 | 5 | 4 | $1,000.00 | 31 | $1,000.00 |
| 2019 | 4 | 4 | $1,112.50 | 29 | $1,000.00 |
| 2020 | 1 | 1 | $1,068.96 | 8 | $1,034.48 |
| 2021 | 5 | 5 | $816.33 | 29 | $816.33 |
| 2022 | 8 | 8 | $1,000.00 | 40 | $1,000.00 |
| 2023 | 7 | 6 | $1,025.00 | 41 | $1,000.00 |
| 2024 | 2 | 2 | $805.00 | 9 | $1,080.00 |
| 2025 | 3 | 3 | $1,120.00 | 13 | $1,120.00 |
| 2026 | 4 | 4 | $1,887.94 | 21 | $1,130.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 7 | $1,200.00 | 51 | $1,300.00 |
| Cabarrus | 8 | $500.00 | 50 | $510.00 |
| Forsyth | 7 | $816.33 | 46 | $1,000.00 |
| Rockingham | 6 | $1,105.00 | 36 | $1,000.00 |
| Wake | 6 | $1,000.00 | 35 | $1,050.00 |
| Alamance | 4 | $800.00 | 23 | $1,500.00 |
| Wilkes | 3 | $1,068.96 | 18 | $1,000.00 |
| Randolph | 3 | $1,000.00 | 18 | $757.50 |
| Robeson | 3 | $1,120.00 | 15 | $1,000.00 |
| Mecklenburg | 3 | $1,125.00 | 15 | $1,125.00 |
| Nash | 3 | $1,000.00 | 14 | $1,000.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 26 | $1,000.00 |
| 1 to 2 | 27 | $1,000.00 |
| 3 to 6 | 27 | $1,000.00 |
| 6 to 109 | 27 | $600.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 SEP 2026 | C205214 | Wilkes | 4 | $1,080.00 | $1,000.00 | 3 | JAMES R VANNOY & SONS CONSTRUCTION COMPANY, LLC | NCDOT |
| 18 AUG 2026 | C204877 | Rutherford | 6 | $1,000.00 | $1,000.00 | 7 | R E BURNS & SONS CO INC | NCDOT |
| 23 JUL 2026 | C205144 | Yancey, Mitchell | 3 | $2,695.88 | $2,695.88 | 1 | AMES CONSTRUCTION INC | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 15 | $3,624.83 | $2,000.00 | 10 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 18 NOV 2025 | C205069 | Robeson | 2 | $1,120.00 | $1,060.00 | 6 | S&C CONSTRUCTION LLC | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 1 | $1,500.00 | $1,500.00 | 3 | BLYTHE CONSTRUCTION INC | NCDOT |
| 19 AUG 2025 | C204829 | Rockingham | 1 | $500.00 | $857.50 | 4 | BLYTHE CONSTRUCTION INC | NCDOT |
| 18 JUN 2024 | C204929 | Rockingham | 2 | $1,110.00 | $1,095.00 | 4 | SMITH-ROWE, LLC | NCDOT |
| 28 MAY 2024 | C204913 | Forsyth | 2 | $500.00 | $1,000.00 | 5 | APAC ATLANTIC INC SMITH ROWE LLC JV | NCDOT |
| 19 DEC 2023 | C204842 | Union | 8 | $505.05 | $1,107.65 | 5 | K. WEST GROUP, LLC DBA | NCDOT |
| 18 JUL 2023 | C204725 | Nash | 4 | $1,000.00 | $1,000.00 | 8 | S T WOOTEN CORPORATION | NCDOT |
| 18 JUL 2023 | C204786 | Wake | 6 | $1,050.00 | $1,075.00 | 4 | CONTI CIVIL LLC | NCDOT |
| 18 JUL 2023 | C204764 | Robeson | 2 | $2,525.00 | $1,625.00 | 6 | SMITH-ROWE, LLC | NCDOT |
| 18 APR 2023 | C204813 | Guilford | 1 | $1,000.00 | $1,100.00 | 7 | ZACHRY CONSTRUCTION CORPORATION | NCDOT |
| 18 APR 2023 | C204793 | Rockingham | 1 | $1,188.00 | $1,100.00 | 7 | W C ENGLISH INCORPORATED | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.