Subdrain fine aggregate unit price, North Carolina
Low bidders on NCDOT contracts carried a median of $81.85 per CY for item 2033000000-E, subdrain fine aggregate, over the 24 months to 20 OCT 2026, across 4 low bids. Half of all 26 bids fell between $65.00 and $101.50.
- Owner
- North Carolina DOT
- Item
- 2033000000-E
- Unit
- CY
- Latest letting
- 15 SEP 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 43 | 43 | $44.00 | 213 | $50.00 |
| 2014 | 31 | 30 | $41.50 | 168 | $44.55 |
| 2015 | 14 | 14 | $51.15 | 91 | $52.00 |
| 2016 | 7 | 7 | $40.00 | 35 | $45.00 |
| 2017 | 7 | 7 | $50.00 | 44 | $50.00 |
| 2018 | 9 | 8 | $48.00 | 48 | $45.00 |
| 2019 | 5 | 5 | $52.00 | 23 | $50.94 |
| 2020 | 3 | 3 | $55.00 | 11 | $57.32 |
| 2021 | 7 | 6 | $68.00 | 37 | $61.35 |
| 2022 | 4 | 3 | $82.50 | 11 | $70.05 |
| 2023 | 5 | 5 | $104.00 | 14 | $102.00 |
| 2024 | 1 | 1 | $33.50 | 7 | $33.50 |
| 2025 | 4 | 2 | $71.85 | 17 | $78.70 |
| 2026 | 2 | 2 | $119.00 | 9 | $75.50 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 9 | $59.15 | 61 | $52.00 |
| Wake | 7 | $45.00 | 42 | $45.45 |
| Henderson | 7 | $55.00 | 34 | $50.00 |
| Cabarrus | 5 | $50.00 | 31 | $50.00 |
| Johnston | 4 | $61.50 | 29 | $50.00 |
| Rowan | 5 | $25.00 | 29 | $50.00 |
| Cleveland | 3 | $47.00 | 29 | $53.00 |
| Rockingham | 6 | $53.50 | 28 | $50.31 |
| Mecklenburg | 6 | $62.50 | 27 | $55.00 |
| Wilkes | 6 | $39.50 | 24 | $40.00 |
| Randolph | 3 | $35.00 | 21 | $35.00 |
| Richmond | 4 | $50.97 | 20 | $47.75 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 8.40 to 20 | 34 | $50.00 |
| 20 to 84 | 34 | $50.00 |
| 84 to 201.60 | 34 | $51.00 |
| 205 to 8,800 | 34 | $50.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 SEP 2026 | C205203 | Wayne | 33.60 | $85.00 | $72.75 | 6 | LEGION ASPHALT INC | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 252 | $153.00 | $102.00 | 3 | BRANCH CIVIL INC | NCDOT |
| 18 NOV 2025 | C205118 | Mecklenburg | 34 | $78.70 | $111.00 | 5 | TRUEROCK CONSTRUCTION LLC | NCDOT |
| 21 OCT 2025 | C205116 | Rockingham | 34 | n/a | $54.80 | 2 | SMITH-ROWE, LLC | NCDOT |
| 18 FEB 2025 | C204883 | Rutherford | 126 | n/a | $80.70 | 5 | KEMP SIGMON CONSTRUCTION CO INC | NCDOT |
| 21 JAN 2025 | C204760 | Cumberland | 168 | $65.00 | $65.00 | 5 | FSC II LLC DBA FRED SMITH COMPANY | NCDOT |
| 28 MAY 2024 | C204861 | Lenoir | 290 | $33.50 | $33.50 | 7 | S T WOOTEN CORPORATION | NCDOT |
| 19 DEC 2023 | C204887 | Cherokee | 336 | $104.00 | $117.00 | 2 | WRIGHT BROTHERS CONSTRUCTION COMPANY INC | NCDOT |
| 21 NOV 2023 | C204471 | Wilkes | 340 | $83.75 | $101.88 | 2 | BRANCH CIVIL INC | NCDOT |
| 18 JUL 2023 | C204851 | Cleveland | 168 | $105.00 | $90.00 | 4 | AMES CONSTRUCTION INC | NCDOT |
| 18 JUL 2023 | C204786 | Wake | 168 | $100.00 | $81.00 | 4 | CONTI CIVIL LLC | NCDOT |
| 18 JUL 2023 | C204176 | Mecklenburg | 84 | $105.00 | $75.00 | 2 | POLIVKA INTERNATIONAL COMPANY, INC. | NCDOT |
| 20 DEC 2022 | C204435 | Pender | 40 | n/a | $50.00 | 3 | S & C CONSTRUCTION LLC | NCDOT |
| 20 DEC 2022 | C204800 | Stokes | 67.20 | $68.83 | $76.91 | 2 | SMITH-ROWE, LLC | NCDOT |
| 12 SEP 2022 | C204781 | Guilford | 125 | $87.69 | $87.69 | 1 | JOINT VENTURE APAC-ATLANTIC, INC/SMITH-ROWE, LLC JV | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.