Temporary mulching unit price, North Carolina

Low bidders on NCDOT contracts carried a median of $1,597.15 per ACRE for item 6015000000-E, temporary mulching, over the 24 months to 20 OCT 2026, across 126 low bids. Half of all 650 bids fell between $1,200.00 and $1,900.00.

Owner
North Carolina DOT
Item
6015000000-E
Unit
ACRE
Latest letting
20 OCT 2026
$1,597.15Low bidder's median, per ACRE
$1,600.00Median of all bids, per ACRE
133Contracts in the window

By year of letting

Temporary mulching, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2013111110$890.00559$850.00
20146865$800.00377$800.00
20155856$800.00349$848.41
20165252$1,000.00262$1,000.00
20174343$900.00236$1,053.15
20186161$1,060.50276$1,060.50
20193030$1,093.53142$1,103.91
20201717$900.0096$900.00
20215956$895.00304$950.00
20225857$1,530.10236$1,500.00
20234745$1,400.00215$1,470.00
20245245$1,700.00255$1,650.00
20256359$1,500.00319$1,575.00
20265956$1,600.00273$1,650.00
Temporary mulching, NCDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By county

Temporary mulching, NCDOT: unit prices by county, last 24 months
CountyLow bidsLow-bid medianAll bidsMedian, all bids
Wake7$1,890.0042$1,861.00
Mecklenburg6$1,207.5040$1,212.50
Forsyth6$1,875.0035$1,085.00
Rockingham7$1,500.0031$1,785.00
Wayne4$1,793.5026$1,765.50
Guilford5$1,600.0025$1,545.03
Rutherford4$1,300.0024$1,445.00
Cumberland4$1,226.5016$1,187.50
Brunswick3$1,200.0015$1,200.00
Haywood3$1,782.5013$1,999.81
Polk3$1,928.1411$2,040.88
New Hanover3$1,050.008$1,825.00
Temporary mulching, NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Temporary mulching, NCDOT: low bidder's median by quantity band
Quantity (ACRE)Low bidsLow-bid median
0.20 to 531$1,800.00
5.12 to 12.5032$1,383.45
12.60 to 23.5031$1,500.00
24 to 67732$1,599.53
Temporary mulching, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest NCDOT contracts carrying Temporary mulching
LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C205216Martin5.50$1,275.00$1,487.504BARNHILL CONTRACTING CONCDOT
20 OCT 2026C205207Pender4.80$850.00$1,340.004S T WOOTEN CORPORATIONNCDOT
20 OCT 2026C204338Wake52$2,000.00$1,717.358BLYTHE CONSTRUCTION INCNCDOT
24 SEP 2026C205140New Hanover1$1,002.86$1,002.861BALFOUR BEATTY INFRASTRUCTURE INCNCDOT
15 SEP 2026C205206Onslow17.50$1,600.00$2,200.003BARNHILL CONTRACTING CONCDOT
15 SEP 2026C205203Wayne14$750.00$1,225.006LEGION ASPHALT INCNCDOT
15 SEP 2026C204349Wake, Durham28$1,400.00$1,400.004BLYTHE CONSTRUCTION INCNCDOT
15 SEP 2026C204990Randolph12.50$1,500.00$1,610.009APAC ATLANTIC INC THOMPSON ARTHUR DIVISIONNCDOT
15 SEP 2026C205214Wilkes5$1,080.00$1,080.005JAMES R VANNOY & SONS CONSTRUCTION COMPANY, LLCNCDOT
15 SEP 2026C204947Caldwell40.50$1,589.00$1,580.003BRANCH CIVIL INCNCDOT
18 AUG 2026C205195Catawba30$1,595.24$1,592.624BLYTHE DEVELOPMENT LLCNCDOT
18 AUG 2026C205205Robeson18$945.00$922.502BMCO CONSTRUCTION INCNCDOT
18 AUG 2026C205202Guilford3$1,600.00$1,595.005TRIANGLE GRADING & PAVING INCNCDOT
18 AUG 2026C204504Watauga44.50$1,828.00$1,750.003BRANCH CIVIL INCNCDOT
18 AUG 2026C204877Rutherford1$1,000.00$1,900.008R E BURNS & SONS CO INCNCDOT
Latest NCDOT contracts carrying Temporary mulching

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.